![CommScope COWO Installation Instructions Manual Download Page 7](http://html1.mh-extra.com/html/commscope/cowo/cowo_installation-instructions-manual_2643562007.webp)
7
D
Cable management pre-assembled cable (drop cable)
5.5
Up to 2 SC-Adapter or 1 LC-Adapter can be positioned at the
front face or inside the box.
5.6
Bottom drop cable entry.
6
Strain relief for Aramid-Fibers
A
Strain relief first cable (75 mm)
5.7
Rear drop cable entry.
6.1
Cut the Aramid-Fibers to length as shown above. Put the
Aramid-Fibers through the slot of the strain relief as shown and push the
fibers on both sides of the strain relief down. Ensure that all fibers are
underneath the slot. The length of Aramid-Fibers on the left and right
hand side of the strain relief should be about the same. Then turn the
strain relief clockwise using a cross-head screwdriver until the Aramid-
Fibers are under tension and properly wound up.
Strain relief
first cable