CHAIN REPLACEMENT 

a.  When replacing load chain, the two chains 

must be exactly the same length. 

b.  The starting chain link on each chain must be 

simultaneously fed into two lifting load 
sheaves. 

c.  The starting links must be placed over the top 

of the load sheave in a horizontal position to 
permit end attachment without twisting the 
chain. 

d.  The second link of chain will be a standing link 

of chain; this link should have the weld furthest 
away from the center of the load sheave. 

e.  See Figure 2 for chain reeving. 
f.  Use only chain supplied by Chester Hoist. 
g.  See Chain Container Installation Notes for 

instructions for loading chain into a chain 
container. 

a.  Refer to Figure 3. 

 
 
 
 
 

 
 

b.  To enable the two independent chains to lift 

the bottom block evenly, the large gears and 
load sheaves must first be timed as Illustrated. 
Then both gears must be timed 
simultaneously with the shaft pinions. This 
timing procedure is only necessary when the 
gears have been disengaged during 
disassembly, Figure.3. 

FUNCTION TESTING 

After load sustaining parts have been altered, replaced 
or repaired, the hoist should be load tested. The hoist 
should be tested using 100 percent of rated load. 

 

 

 

 

 

 

TABLE 2: LUBRICATION 

PART 

LUBRICANT 

INSTRUCTIONS 

FREQUENCY 

Transmission 

Mobilgear #634 
Synthetic or Equivalent 
(see parts manual for 
quantity) 

Drain from drain plug in bottom of 
housing. Fill to level plug on side of 
housing. 

After initial 50 hours of 
operation, then every 3 
months or 500 hours. 

Motorized 
Trolley Gear 
Box 

Mobilgear #634 
Synthetic or Equivalent 
(see parts manual for 
quantity) 

Drain from drain plug in bottom of 
housing. Fill to level plug on side of 
housing. 

After initial 50 hours of 
operation, then every 3 
months or 500 hours. 

Load Block 

NLGI No. 2 Grease 

Lubrication is required only when sheave 
pin contains grease fittings. 

30 days 

Load Chain 

Intermediate oils 
preferably with EP 
Additives 

Bonded Lubricants such 
as Dow Molykote M-77 
or LPS Chainmate 

Immerse in oil or swab with oil soaked 
rag. Wipe off excess oil. Maintain chain 
rust-free. 

Use in place of oil, if oil residue is 
objectionable. 

Daily 

*Trolley 
Wheels 

NLGI No. 2 Grease 

Wheels will have grease fittings. (see 
note below) 

After prolonged use or 
reassembly. 

Spur Gears 

NLGI No. 2 Grease 

Brush on exposed gears. 

Weekly 

*Not required on units equipped with sealed ball bearings. (Wheels will not have grease fittings.) 

Summary of Contents for CHESTER HOIST EL-680

Page 1: ..._____ Rated Load _________________________________________ RATED LOADS 1 TO 24 TONS Follow all instructions and warning for inspecting maintaining and operating this hoist The use of any hoist present...

Page 2: ...and parts services through a network of Master Parts Depots and Service Centers that are strategically located in the United States and Canada These facilities have been selected on the basis of their...

Page 3: ...of a hoist can create a potentially hazardous situation which if not avoided could result in minor or moderate injury To avoid such a potentially hazardous situation the operator shall 1 Maintain a fi...

Page 4: ...ecialized experience and study is essential to safe rigging operations For rigging information we recommend consulting a standard textbook on the subject Table of Contents Safety Precautions 3 5 Gener...

Page 5: ...s sizes of runway beams Other Chester Hoists and trolleys are built to fit a runway specified by our customers Regardless it is the customer s responsibility to apply such engineering calculations or...

Page 6: ...The hoist chain should not be wrapped around the load 2 The load should be attached to the hook by means of slings or other approved devices 3 The slings or other approved devices shall be seated prop...

Page 7: ...arts for signs of pitting or any deterioration of controls limit switches and push button station h Check chain container See Chain container installation notes ANNUAL INSPECTION Inspect the following...

Page 8: ...small loop of loose chain remains when the geared limit switch prevents further travel The peddle limit switch only acts If this switch falls 2 Brake Adjustment See Figure 1 a Remove nuts 1 and cover...

Page 9: ...parts have been altered replaced or repaired the hoist should be load tested The hoist should be tested using 100 percent of rated load TABLE 2 LUBRICATION PART LUBRICANT INSTRUCTIONS FREQUENCY Transm...

Page 10: ...IN REEVING 1 1 2 2 5 6 Ton 3 4 8 10 12 Ton 16 20 24 Ton FIGURE 3 LOAD SHEAVE TIMING T indicates three timing marks in alignment Unloaded Loop Loaded Side Unloaded Loop Loaded Side Unloaded Loop Loaded...

Page 11: ...d be traversed the entire length of the beam to check for beam interference pointe proper side clearance and effectiveness of the beam stops If everything is satisfactory the procedure should be repea...

Page 12: ...for wear Hook Moves in Wrong Direction 1 Three phase reversal 2 Improper connections 1 Reverse any two wires except the green ground wire at the power source 2 Check all connections against wiring dia...

Page 13: ...mation 1 Serial Number of your hoist see Figure 2 tor location 2 Your power supply voltage phase and cycles 3 Title of illustration for example 3 4 Ton bottom block assembly 4 Figure Number Part Name...

Page 14: ...he load block up allowing the hoist mechanism to fill the container Verify the chain is loading properly into the container WARNING Never load chain into the container by hand Hand loading will cause...

Page 15: ...WARRANTIES SET FORTH ABOVE SELLER MAKES NO OTHER WARRANTIES WITH RESPECT TO THE GOODS OR ANY REPLACEMENT PARTS WHETHER EXPRESSED OR IMPLIED INCLUDING ANY WARRANTIES OF MERCHANTABILITY FITNESS FOR A P...

Reviews: