Coleman 36MWL Installation Instructions Manual Download Page 7

 

For more information, visit www.desatech.com

FLASHING INSTALLATION: (V6F-8DM or V12F-8DM) 

Determine the flashing to be used with the roof-opening chart.  
Slide flashing over pipe until base is flat against roof.  Replace 
as many shingles as needed to cover exposed area and flashing 
base.  Secure in position by nailing through shingles (see 
figure 12). 
DO NOT NAIL THROUGH FLASHING CONE. 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
 
 
 
INSTALLING FLASHING ON A METAL ROOF: 

When installing the flashing on a metal roof it is required that 
putty tape be used between the flashing and the roof.  The 
flashing must be secured to the roof using #8 x ¾” screws and 
then sealed with roof coating to prevent leakage through the 
screw holes.  A roof coating must also be applied around the 
perimeter of the flashing to provide a proper seal. 

STORM COLLAR INSTALLATION: (SC1 or SC2) 

Place storm collar over pipe and slide down until it is snug 
against the open edge of the flashing (see figure 13).  Use SC1 
for all round terminations and SC2 for all terminations with 
slip sections.  Apply waterproof caulking to all seams and 
notches around storm collar and also at base around shingles. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Note: Storm collar is required but can be installed after the 
home is sited. 
 

TERMINATIONS / SPARK ARRESTOR: 

The fireplace system must be terminated with the listed round 
top terminations.  In any case, refer to the installation 
instructions supplied with the termination.  The terminations 

approved for this fireplace are the RT-8DM and RTL-8DM. 
Figure 18 shows an RTL-8DM round top termination. 
IMPORTANT: Terminations are required but can be installed 
once the manufactured house is sited. 

 
Terminations with 16” slip pipe sections are available.  The 
RTT-8DM and RTTL-8DM are approved for flashing 
installations. When needed, these adjustable terminations may 
be used in combination with the pipe assembly to achieve the 
correct chimney height. 

NOTE:

 In the rare instance there is a problem with side driven 

rain or wind or the chimney is not drafting properly, an ADS-
8DM Anti Draft Shield can be used with round terminations. 

 
10 FOOT RULE: 

All flue gas outlet of chimney termination must extend a 
minimum of 3 feet in height above the highest point where it 
passes through the roof and must be at least 2 feet above the 
highest point of the roof that is within a horizontal distance of 
10 feet (see figure 15). 
 
 

 
 
 
 
 
 
 
 
 
 
 
 

Figure 12 

 

Figure 13 

Figure 15 

 

Figure 14 

CAUTION:

 Do not seal openings on the rooftop flashing. 

Follow the installation instructions provided with the 
termination being used. 

Summary of Contents for 36MWL

Page 1: ...le not for purpose of resale from the manufacturer permanently located manufactured mobile home where not prohibited by local codes A DESA hood must be installed when using a vent free gas log heater...

Page 2: ...HEARTH EXTENSION PG 3 6 OUTSIDE AIR KIT INSTALLATION PG 4 7 FAN KIT ASSEMBLY PG 4 8 CHIMNEY PIPE INSTALLATION PG 4 5 6 9 TERMINATIONS PG 6 10 FINISHING YOUR FIREPLACE PG 7 11 MANTELS PG 7 12 GLASS DO...

Page 3: ...will make installation easier 4 An outside air kit is included with this fireplace For more details refer to section on outside air kit installation on page 4 WARNING DO NOT INSTALL IN A BEDROOM MINIM...

Page 4: ...28ga minimum to prevent corrosion STEP 6 Using screws or nails secure the fireplace to the framing through flanges located on the sides of the fireplace see figure 4 HEARTH EXTENSION A hearth extensi...

Page 5: ...contents of these kits are listed under accessories on page 11 Most chimney systems for manufactured houses require a standard straight installation as described in this section If an uncommon offset...

Page 6: ...it onto the firestop using holes provided see figure 10 The row of holes on the sides of the thimble is provided to allow for pitch variances Position the firestop assembly and thimble to desired angl...

Page 7: ...but can be installed after the home is sited TERMINATIONS SPARK ARRESTOR The fireplace system must be terminated with the listed round top terminations In any case refer to the installation instructi...

Page 8: ...16 from the wall the fireplace is installed in This combustible material can butt up against the side of the fireplace i e 1 from the fireplace opening OPERATING GUIDELINES AND MAINTENANCE INSTRUCTION...

Page 9: ...ce cement Install the decorative gas appliance or cap off gas line if desired The gas pipe is intended for connection to an unvented vent free or a decorative gas appliance vented gas log If you wish...

Page 10: ...d to rafters or joists see figure 22 details a b 3 Maximum length of pipe between supports return elbow or 12S 8DM is 6 of angled run Maximum of two 2 6 angled run sections per chimney system see figu...

Page 11: ...to lock it in place see figure 25 FOR FURTHER OPERATING GUIDELINES INSTRUCTIONS AND WARRANTY INFORMATION PLEASE REFER TO YOUR HOMEOWNERS GUIDE OR CONTACT YOUR AUTHORIZED DEALER TECHNICAL SERVICE You m...

Page 12: ...CPMH A ACB 8 vent kit 9 vent kit 9 vent kit 36 8DM 36 Double Wall Pipe 2 1 2 24 8DM 24 Double Wall Pipe 1 3 0 18 8DM 18 Double Wall Pipe 0 0 2 FST A Adjustable Firestop Thimble 1 1 1 6F 8 Roof Flashi...

Reviews: