22)  Once the tower is standing leave the crane attached and attach the guy wire 

cables to the lifting eyes. Each cable will have its own "D" shackle, Thimble, 
Rope Clamp (x2) and Turnbuckle. 

23)  Use a high reach or cherry picker to remove the crane from the Pull Up bracket. 

24)  Install the red base covers. 

25)  Install the Striker, Skill Select and Permanent power. 

26)  Power Game up and spray the PCBs and into the power supplies with the 

moisture displacer supplied. 

27)  Run a bead of silicone around the base and tower section. This is another critical 

weatherproofing step. 

 

Tools Needed for Hi-Striker X-Treme 

 

7/8" open/box end wrench (Tower/Base Hardware) 

 

3/4" open/box end wrench (Skill Select Mounting Hardware) 

 

9/16" open/box end wrench (Guy wire Bracket Hardware) 

 

7/16" open/box end wrench (PCB Enclosure) 

 

3/8" drive ratchet 

 

7/8" socket (Pocket Top Sign Bolts) 

 

3/4" socket (Packing hardware) 

 

9/16" socket (Guy wire hardware) 

 

1/2" socket (New Style Park Guy wire Clamp) 

 

1/8" Allen Wrench / Bit (Top Sign Back Cover) 

 

Large Crescent Wrench (Base & Striker Mounting, Turnbuckle nuts) 

 

Other Items (suggested) 

 

Cordless Drill w/ spare batteries (Unpacking) 

 

Magnetic bit holder and Phillips tip (Unpacking) 

 

Wire Cutters (Zip Ties/Wires) 

 

Standard Blade Screwdriver 

 

Phillips Screwdriver 

 

Small Slip Joint Pliers 

 

Utility Knife 

 
 

Summary of Contents for Hi-Striker X-treme

Page 1: ...he black gasket on either side of the LED board to expose the screws Once the tower sections are close enough plug the upper LED board of the lower section into the LED board on the upper section short cable w red connector 6 Reinstall LED board screws and secure LED gasket back into place 7 Bolt the tower sections together using the 4 3 8 x 1 hardware included in the hardware kit 8 Once the tower...

Page 2: ...ign onto the tower section using the hardware provided and BOTH black gaskets Re install the back panel on the Top Sign 18 Install the guy wire cables The longest ones go to the upper section and the shorter ones go to the lower section For a 45 game there will be 3 different lengths and 3 guy wire attachment points on the tower 19 Install the Pull Up cable to the same stud as the guy wire cable o...

Page 3: ...ritical weatherproofing step Tools Needed for Hi Striker X Treme 7 8 open box end wrench Tower Base Hardware 3 4 open box end wrench Skill Select Mounting Hardware 9 16 open box end wrench Guy wire Bracket Hardware 7 16 open box end wrench PCB Enclosure 3 8 drive ratchet 7 8 socket Pocket Top Sign Bolts 3 4 socket Packing hardware 9 16 socket Guy wire hardware 1 2 socket New Style Park Guy wire Cl...

Page 4: ...n experienced operator is required Cherry Picker 30 35 reach to lift a person up to the back of the tower to disconnect the crane from its attachment points Fencing To securely enclose the Hi Striker play field before operation Labor Please have adequate staff to help with the basic assembly and to erect the tower Power Please have the required power 220v 20amp run to the location Also temporary p...