3 Positioning
During positioning consider these elements:
•
Technical spaces requested by the unit
•
Electrical connections
•
Water connections
•
Spaces for air exhaust and intake
3.1 Functional spaces
Functional spaces are designed to:
•
guarantee good unit operation
•
carry out maintenance operations
•
protect authorized operators and exposed people
Respect all functional spaces indicated in the DIMENSIONS section.
Double all functional spaces if two or more unit are aligned.
3.2 Positioning
Units are designed to be installed:
•
INTERNAL
•
in fi ed positions
Limit vibration transmission:
•
use antivibration devices on unit bearing points
•
install fl xible joints on the hydraulic connections
Choose the installation place according to the following criteria:
•
Customer approval
•
safe accessible position
•
technical spaces requested by the unit
•
max. distance allowed by the electrical connections
•
Avoid installations in places subject to floodin
•
verify unit weight and bearing point capacity
•
verify that all bearing points are aligned and leveled
3.3 Saftey valve gas side
The installer is responsible for evaluating the opportunity of installing drain tubes, in conformity with the local regulations in force (EN 378).
Summary of Contents for WSHN-XEE2 10.2
Page 7: ...WSHN XEE2 10 2 120 2 7 2 3 Instructions for disassembly Only with options MOBMAG...
Page 14: ...14 WSHN XEE2 10 2 120 2 5 5 Connections performer by customer dwg n WD8U02400...
Page 43: ...WSHN XEE2 10 2 120 2 43 9 3 Source side 3 way modulating valve...
Page 44: ...44 WSHN XEE2 10 2 120 2 9 4 Source side 2 way modulating valve...
Page 45: ...WSHN XEE2 10 2 120 2 45 9 5 VALVE FOR DOMESTIC HOT WATER...