Installation Instruction
4.4 Rectangular Tube- Landscape Installation
4.4.1 Fix the 3 pcs PM3-A Rectangular Tube- Landscapes at Rectangular Tube-Master with 2 pcs
M12*100 hex bolts
,
2 pcs M12 nuts , 2 pcs plain washers 12 and 2 pcs spring washers 12. Do not
fasten the Nut until 3 Rectangular Tube- Landscapes aligned.
Note: Adjust the Rectangular Tube- Landscapes until the dimension D1=D2=D3=D4.
Recommended torque for M12 bolts is 50~55 N·m
4.2 ECO Rail Installation
Fix the ECO Rail to Rectangular Tube-Master with M8*20 hex socket bolt, Z module, Spring washer 8,
Washer 8.
Note: Make sure that the rail ends align horizontally and that the rails are parallel to each other.
Recommended torque for M8 bolts is 18~20 N·m
Note:ECO Rail of 3150 mm is a standard length in this system, which can be suitable for up to
1002 mm wide panel. If the panels are over 1002 mm (less than 1100 mm) wide, the required
minimum rail length is:
(panel width-1002)*3+3150 (mm).
For example, panels are 1050 mm wide. The required minimum rail length is (1050-1002)*3+3150
= 3294 mm. For convenience, the rail length is rounded up to 3300 mm (multiple of 50 mm).