15
Revision date: 07.03.14
CLEARSPAN
™
PREMIUM MOO-TELS
The drop-down curtain requires a ribbon board to secure its
upper section and a baseboard to secure its lower section.
The materials for these components are not included and
are
supplied by the customer
.
BASEBOARDS AND RIBBON BOARDS
The example above shows the required ribbon board and
baseboard as attached to the frame.
ATTENTION:
Consult the Main Cover Details diagram in
the Quick Start section of this manual to determine where
to install the ribbon board.
The ribbon board consists of two runs of material; the first
is a 2" x 4" or 2" x 6" board attached to the building frame
and the second is a 1" x 4" board attached to the first
board. These boards, when assembled properly, provide
a channel that secures the curtain when it is in the up or
closed position. Boards are secured to the frame using the
supplied 1/4" x 4" carriage bolts and to each other using the
FA4652 supplied fasteners.
Ribbon Board
Baseboard
Rafter
2" x 6" or
2" x 4" Board
1" x 4" Board
FA4652
Wood
Screws
1/4" x 4"
Carriage
Bolts
U-Channel
The diagram
shows a customer-
supplied ribbon
board as attached
to the frame
A customer-supplied baseboard and retaining board are
also required to attach the curtain's lower edge. See the
exploded view that follows.
The baseboard runs the length of the frame at ground level.
The retaining board secures the curtain to the baseboard.
The baseboard and retaining board are supplied by the
customer.
Fasteners (1/4" x 4" carriage bolts and FA4652 wood
screws) are included. Depending on board width, use 2
carriage bolts per rafter connection for the baseboard and
ribbon board. Evenly space the wood screws at 24".
FRAME CHECK AND RIBBON BOARD INSTALLATION
1. Verify that the baseboard is installed properly at ground
level. The baseboard must be level for the drop-down
curtain to install and function properly.
2. Gather the boards needed for the retaining board of the
baseboard. See diagram above.
3. Attach the first board of the two-piece ribbon board to
the frame at the required height for the curtain. See the
main cover details diagram in the Quick Start section
for the drop-down curtain height.
4. Use the diagram to the left to install the second board
of the ribbon board. Attach to the first board using
FA4652 wood screws.
5. Recheck the frame assembly for sharp edges or
clamps and bolts that may interfere with the installation
of the curtain. File or tape sharp edges as needed.
6. Continue with the installation of the end frame and end
panels.
End Panel of Shelter
Curtain
Panel
Ground Level
Baseboard and
Retaining Board