ClearFox®Control Unit CU-M

o

Level measurement via Filling. If below switching level 1 => eco

o

Filling

o

Level measurement via Filling. If above switching level 2 => overfill alarm

o

Denitrification (can be deactivated by setting step time to 0s)

o

Aeration

o

Sludge (before Settling, option, can be deactivated by setting step time to 0s) 

sludge return will not take place within the first 90 days after bringing into
service. This value can be changed, the parameter is called 

Biology Build-Up

Time

.

o

Settling

o

Sludge (after Settling, option, can be deactivated by setting step time to 0s) 

sludge return will not take place within the first 90 days after bringing into
service. This value can be changed, the parameter is called 

Biology Build-Up

Time

.

o

Clearwater removal

o

Option: Check DI1, if closed => overfill alarm (if no float switch is connected,
there will not be an alarm)

-

Eco mode

o

Aeration

o

Level measurement via Filling. If above switching level 1 => normal

o

Each 6 eco cycles (frequency can be changed) => At least one normal mode

9.1.2

 

Water level measurement 

Water level measurement at this process is performed using the filling airlift in the pretreatment 
tank.  

If the level before filling is higher than the calibrated value plus Offset 1, filling will be 
performed, and the control unit will follow the normal mode program. If the level is lower, filling 
will not be performed, and the program follows the eco mode process.  

If the level after filling is higher than the calibrated value plus Offset 2, this means, filling could 
not be performed. Likely the problem was that the reactor is (still) full because clearwater 
removal did not work and thus the water pumped from the pretreatment to the reactor during 
filling simply flowed back. An overfill alarm will be signalized in this case.  

calibrated minimum 

Offset 1 

(Eco / Normal) 

Offset 2 

(overfill alarm) 

Figure 4: Pretreatment tank with filling airlift and calibrated minimum, Offset 1 and 2 

Summary of Contents for CU-M

Page 1: ...1 Quick Start Guide ClearFox Control Unit CU M...

Page 2: ...ed Bed 6 6 5 Drippling filter D Tropfk rper 6 7 Connecting to Wi Fi 7 7 1 Connecting the control unit to the internet via Wi Fi ST mode 7 8 Alarm handling 8 9 Process overviews 8 9 1 Air SBR 8 9 1 1 P...

Page 3: ...ClearFox Control Unit CU M 3 12 2 Transfer via USB 16...

Page 4: ...where you d type www google com http 192 168 117 1 o Username for service login service o Password 1111 same as service menu PIN 3 INTRODUCTION The ClearFox Control Unit CU M platform is a powerful fr...

Page 5: ...t the underside of the printed circuit board and close to the mains supply connectors and the fuse mains voltage 230 V Before removing the casing cover it is necessary to pull the mains supply connect...

Page 6: ...jection Aerator Connected to the electric socket of the ClearFox Control Unit CU M Out 5 electric socket Sludge return Pump Out 3 Valve Out 3 Blower BonFlash alarm beacon is connected to the terminals...

Page 7: ...not forget to push Apply Wi Fi Settings control unit restarts The ClearFox Control Unit CU M can run Wi Fi in Access Point AP and in Station Mode ST AP Wi Fi hotspot without internet connection intra...

Page 8: ...deactivates the Buzzer and the BonFlash output The red LED remains on and the last alarm remains in the Status Screen until the reason for the alarm is gone e g float switch is down again or until th...

Page 9: ...Eco mode o Aeration o Level measurement via Filling If above switching level 1 normal o Each 6 eco cycles frequency can be changed At least one normal mode 9 1 2 Water level measurement Water level m...

Page 10: ...re as it cannot suck anymore water 3 Sludge return for some 60s to increase the level in the pretreatment so that the filling airlift can pump properly again 4 Filling for 20s the pressure at this min...

Page 11: ...over DI1 open Eco Via Sludge Pump ON 10s OFF 14 50min or until DI1 closed On timeout step time over DI1 open Eco o Denitrification 0 40min ON 9 20min OFF 60min Total o Aeration 8min ON 12min OFF 9 5h...

Page 12: ...ssure limits 7 350mbar for Blower applied Pump Out 3 Current limits 300 1800mA for pump applied 9 3 ONE TANK SBR 9 3 1 Process steps For the level measurement overfill alarm a manual calibration must...

Page 13: ...ease ask PPU in case you want to activate it Time taken from the settling time example Settling 2h sludge 2min settling will be 1 58h in reality and sludge 2min sludge return after settling can be dea...

Page 14: ...ower applied Via sludge pump Out 3 Current limits for pump 300 1800mA applied CLEARWATER Blower valve Out 1 2 Current limits for Blower 250 900mA valve 50 150mA applied Generic pressure limits 7 350mb...

Page 15: ...mA valve 50 150mA applied Generic pressure limits 7 350mbar for Blower applied Via sludge pump Out 4 Current limits for pump 300 1800mA applied CLEARWATER ON DAY OFF DAY ON NIGHT OFF NIGHT ON HOLIDAY...

Page 16: ...here click on Start update process done 12 2 TRANSFER VIA USB Please mind that the batteries must be connected Please record the pkg Pack file into the root folder of a common USB stick formatted wit...

Reviews: