SECTION 6: CHECK & TEST
1.) Recheck that all the wiring works. Check that all connections are tight and correct to the
manual.
2.) Switch on the power supply to the unit.
3.) Press the
POWER
button on the control box.
4.) Using the wall controls test all the functions to ensure they are working correctly.
If any functions do not work recheck the wiring using sections 4 and 5 of this guide.
5.) Use the remote control to operate the unit, check all the functions.
6.)Finish wall construction work.
E-11
Caution: When the wiring is complete a thorough
“testing cycle” must be performed to check the
operation of the unit PRIOR to the wall / area being
closed up, tiled, and/or bricked.