Leveling:
Picture 22
The installation of the anchor bolts must take place within the same installation day of the
lifter to ensure the structure’s rigidity and perfect installation.
During the test of the lift, no person and no object and / or material must be located near the
two sides and below the lift. If an anomaly occurs, press the «EMERGENCY STOP» button to
stop the the lift immediately. After removing the obstacles, repeat the test.
Use a level to adjust the draft screws on the base pull sides
If the irregularity of the platforms is due to the irregularity of the base, use an iron or concrete
plate to level the base.
When you have given the level, insert the anchor and use an attachment to secure it.
After giving the level, insert the anchor and use a hammer to secure it.
Unscrew the cover of the earth bolts
Turn on the machine with the «MAIN SWITCH» power button.
Press the «UP» button, pay attention to the synchronization and the lifting fluidity.
Check that there is no leakage of oil.
Adjust the parallelism of the base of the two platforms (as shown in Figure 4)
Attach the anchors with an electric percussion drill (the percussion pin is 16) by pocking
a 120 mm hole. Clean the hole before inserting the dowels. (Figure 22)
Use a rubber hammer to insert the dowels into the floor. (It is recommended to proceed
with the insertion of the joints only after the leveling of the floor)
INSTALLATION OF ANCHORING BOLTS:
Lift test:
Picture 22
Picture 23
Summary of Contents for PE 6004
Page 1: ...clas com PONT DOUBLE CISEAUX DOUBLE VERIN 3 5T DOUBLE SCISSOR LIFT DUAL CYLINDER 3 5T PE 6004...
Page 49: ...PE 6001 DOUBLE SCISSOR LIFT 3T PE 6004 DOUBLE SCISSOR LIFT DUAL CYLINDER 3 5T 49 51...
Page 51: ......
Page 52: ......
Page 53: ......
Page 54: ......
Page 55: ......