7. Method Of Operation 

 

Run Mode: 

When the arrow on the handle of the valve is pointed towards the gage (opposite the vessel connection) 
the valve is in the Run Position. 
 

 
 
 
 
 
 
 
 
 

The function of the Run Position is intended for when the gage is in normal operation. This mode positions 
the seating surface of the internal ballcheck towards the armored glass gage allowing the ballcheck to seat 
in the case of a catastrophic event. The pressure differential required to seat the ballcheck is ~5 psi. 
 

Bypass Mode: 

When the arrow on the handle of the valve is pointed in the direction of the process connection the valve is 
in the Bypass Position. 

 
 
 
 
 
 
 
 
 

 
The Bypass Position is intended for use while the gage is being commissioned when there is already liquid 
present in the vessel. This mode of operation positions the internal ball mechanism such that there is a 
retainer plate towards the armored glass gage connection. In this scenario the ballcheck cannot seat as 
the ballcheck seating surface is upstream of the ball. Fluid will flow around the ball, through the retainer 
plate, and into the gage while it is being commissioned.  
 

Closed Mode: 

When the arrow on the handle of the valve is pointed perpendicular to the valve (either pointing up or 
down), the valve is in the closed position.  

 

 
 
 
 
 
 
 
 
 
 

The closed position is intended for use when the operator intends to isolate the gage from the vessel. This 
mode of operation positions internal ball mechanism such that it blocks the process port preventing fluid 
from entering the gage or draining back to the vessel. 
 

Summary of Contents for Jerguson 360 Series

Page 1: ...ay Strongsville OH 44149 USA Telephone 1 440 572 1500 Fax 1 440 238 8828 www Jerguson com sales clark reliance com Installation Operation Maintenance Instructions IOM J500 36 2017 10 360 Series Safety...

Page 2: ...440 572 1500 Fax 1 440 238 8828 www Jerguson com sales clark reliance com Table of Contents 1 INTRODUCTION 3 2 WARRANTY 3 3 ABOUT THIS MANUAL 3 4 INSPECTION AND DELIVERY 3 5 PRODUCT DESCRIPTION 3 6 S...

Page 3: ...all instructions before attempting to install operate or maintain this equipment Only persons certified to perform work described herein should attempt any actions suggested Safety precautions and com...

Page 4: ...IOM J500 36 Jerguson 360 Series 2017 10 4 16633 Foltz Parkway Strongsville OH 44149 USA Telephone 1 440 572 1500 Fax 1 440 238 8828 www Jerguson com sales clark reliance com 6 Specifications...

Page 5: ...ess connection the valve is in the Bypass Position The Bypass Position is intended for use while the gage is being commissioned when there is already liquid present in the vessel This mode of operatio...

Page 6: ...to open the top valve first This allows the pressure of the vessel to equalize with the gage 3 Open the bottom valve to the bypass position This will allow liquid to flow from the vessel through the...

Page 7: ...orn nut lock washer and spacer Secure valve into a vice with the large compression nut facing upward Take care not to damage any of the external components Remove anti rotation pin and discard Use lar...

Page 8: ...he ball mechanism by sliding it off of the stem through the process opening 5 If you wish to replace or remove the internal ballcheck remove the ball retainer clip If not continue to step 6 6 Remove u...

Page 9: ...hrust washer on stem flange Align side with chamfer on ID with face of stem flange Angle the stem and insert into valve body 2 Holding stem flange and washer pressed up against top of body install 3 n...

Page 10: ...Torque nuts in X pattern to 15 20 in lb Visually confirm gland follower is level 4 Install Handle Back onto valve and cycle the stem several times Leave valve handle in the closed position 5 Replace...

Page 11: ...ke shown Place the new upstream seat and seal into the inlet gland opening 8 Insert the inlet gland assembly from the previous step into the valve as shown 9 Secure valve into a vice with the large co...

Page 12: ...IOM J500 36 Jerguson 360 Series 2017 10 12 16633 Foltz Parkway Strongsville OH 44149 USA Telephone 1 440 572 1500 Fax 1 440 238 8828 www Jerguson com sales clark reliance com...

Reviews: