Electrical Testing 

 

If performing a Zs test at the charge point, the Safevolt 50 will need to be installed and operational and 

the green output LED ON. 

 

If the Safevolt

®

 50 is not operational the CPC will be disconnected from the charge point and the Zs test 

will fail. 

 

For insulation testing, L, N & E should be disconnected from the input of the Safevolt

®

 50. 

Insulation testing will require the circuit to the charge point to be tested in two segments, i.e. supply to 

Safevolt 50 and then Safevolt 50 to Chargepoint. 

 

For each segment the Safevolt

®

 50 should be disconnected from the segment under test and in the case of 

Safevolt

®

 50 to Chargepoint, the charge point disconnected also. 

 

 

 

 

Precautions 

 

 

General 

 

 

The Safevolt

®

 50 unit is designed to isolate the installation PME earth from the charge point CPC in the 

event of a PEN conductor (PME) failure. 

 

 

It is therefore important to check that no part of the CPC circuit on the output side of the Safevolt

®

 50 

unit is connected to any point which is directly or indirectly connected back to the building earth. 

Any such connections will render the Safevolt

®

 50 system ineffective. 

 

For instance, check no secondary earth connection exists between the casing of the charge point and any 

metallic part such as a DB casing or service pipe. 

 

Special care is needed if using SWA cables as described on the next page. 

 

 

Cityline Safevolt 50 User and Installation Manual 

 

                         

Cityline Safevolt 50 User and Installation Manual 

 

                         

CityEV Safevolt® 50 User and Installation Manual 

 

                         

Summary of Contents for Safevolt 50

Page 1: ...Documentation Revision 1 31 September 2020 Copyright 2020 CityEV Limited All Rights Reserved All trademarks are owned by CityEV Limited CityEV Safevolt 50 User and Installation Manual...

Page 2: ...fety Information 3 The CityEV Safevolt 50 5 Safevolt 50 Operation 5 Positioning 7 Removing the cover 7 Connections 8 Electrical Testing 9 Precautions 9 General 9 10 Using SWA cables with Safevolt 50 1...

Page 3: ...ED WITH THE ENGLISH LANGUAGE VERSION WHICH IS POSTED AT WWW CITYEV NET Revision 1 31 Date September 2020 Product Part Number Safevolt 50 About Your System As soon as you open your product record the f...

Page 4: ...tion or service work Do not remove the device cover while the power supply is connected Do not operate the device with the cover removed Do not attempt to repair or replace any part of the device In c...

Page 5: ...le Charging Equipment There is no need to convert to TT or install an isolation transformer Safevolt 50 Operation The Safevolt 50 status indicators are shown and described below During normal operatio...

Page 6: ...50 unit is not weather protected and intended for indoor installation only Figure 2 below shows typical single phase charge point installation using the Safevolt 50 protection unit Safevolt 50 single...

Page 7: ...sed e g flat T E round or SWA types Ensure cables are securely secured by glands or use cable ties if necessary Electrically the unit is connected in series with the charge point supply Removing the c...

Page 8: ...CPC is connected to the left hand lever connectors and the outgoing supply to the charge point is connected to the right hand lever connectors as shown Note Maximum cable size is 6mm2 CityEV Safevolt...

Page 9: ...the charge point disconnected also Precautions General The Safevolt 50 unit is designed to isolate the installation PME earth from the charge point CPC in the event of a PEN conductor PME failure It i...

Page 10: ...oint CPC including the metal case of the Safevolt unit For instance an SWA cable terminated in the charge point case and a building DB with a metallic case will cause such a connection and is not allo...

Page 11: ...onds Earth Fault Trip Reset Automatic Connectors Screw Terminal Max 6mm2 Indicators Output On PME Earth Fault Dimensions Wall mounting 200mm W x 70mm H x 50mm D Weight 750g Environmental Operating Tem...

Page 12: ...1 iv 2018 Electric vehicle charging installations TN systems I hereby declare that the equipment named above is compliant with the relevant sections of the above referenced specifications The unit co...

Reviews: