4-15
Cisco TelePresence System TX9000 and TX9200 Assembly, Use & Care, and Field-Replaceable Unit Guide
OL-27038-01
Chapter 4 Installing And Performing Initial Leveling of the Main Display Structure
Installing Seismic Brackets (Optional), Part Number CTS-TX9K-SEISMIC=
Installing Seismic Brackets (Optional), Part Number
CTS-TX9K-SEISMIC=
You can order an optional seismic bracket kit for the TX9000 and TX9200 that is used to secure the main
display frame to a concrete floor in regions prone to seismic events.
Note
These brackets are not included with the system and you must order them separately. The part number
is CTS-TX9K-SEISMIC= .
The kit includes six rear seismic brackets that are secured to each of the six rear leveling feet on the main
display frames, and two front seismic brackets that are secured to the front, left-most leveling foot on
the left display frame piece, and the front, right-most leveling foot on the right display frame piece.
shows the location of the front and rear seismic brackets.
Figure 4-13
Position of Seismic Brackets
Install the seismic brackets by completing the following steps:
Caution
Do not install the seismic brackets until you have moved the main display structure pieces to their final
position. You will not be able to move the main display structure pieces after you install the seismic
brackets.
Key
Part Description
Qty
1
Rear seismic mounting brackets
6
2
Front seismic mounting brackets 2