Table 4: Accessories Kit
Accessories
PID
Category
Variant
Yes
A920-RCKMT-19
19 inches
ASR-920-20SZ-M
Yes
A920-RCKMT-23-H
23 inches
Yes
A920-RCKMT-ETSI
ETSI
Yes
A920-RCKMT-19
Wall mount
No
NA
Desktop
Yes
A920-CBL-GUIDE
A920-CBL-BRKT-E
(ETSI)
Cable bracket
Yes
A920-DRIP-TRAY
Dip Tray
Tools and Equipment
You need the following tools and equipment to install and upgrade the device and its components:
• ESD-preventive cord and wrist strap
• Antistatic mat or antistatic foam
• Number 1 and Number 2 Phillips-head screwdrivers
• #12-24 pan-head screws to secure the device to the equipment rack.
• Cables for connecting to network ports (based on the configuration)
• Ethernet hub, switch, or PC with a network interface card for connecting to the Ethernet ports
• Console terminal that is configured for 9600 baud, 8 data bits, no parity, no flow control, and 1 stop bit.
• Console cable for connecting to the console port
• Ratcheting torque screwdriver with a Phillips head that exerts up to 30-pound force per square inch
(0.02-kilograms force per square millimeter (kgf/mm2)) of pressure.
• Crimping tool as specified by the ground lug manufacturer
• Wire-stripping tools for stripping both 6 and 14-AWG wires
• Tape measure and level
• Ratcheting torque screwdriver with a Phillips head that exerts up to 15 inch-pounds (1.69 newton meters)
of torque for attaching the ground wire to the device.