Step 6
Repeat step 1 through step 5 for any additional chassis you are installing in the equipment rack.
Step 7
Proceed to the
Grounding the Chassis, on page 60
and ground the chassis.
Grounding the Chassis
Make sure that the chassis is properly grounded prior to installing any chassis sub-components or cards. The
chassis and the equipment rack or telecommunications cabinet that it is installed in must be connected to the
same ground.
Failure to properly ground the chassis could result in personal injury and/or damage to the chassis and its
components.
Caution
ASR 5000 Installation Guide
60
Chassis Installation
Grounding the Chassis
Summary of Contents for ASR 5000
Page 16: ...ASR 5000 Installation Guide xvi About this Guide Contacting Customer Support ...
Page 64: ...ASR 5000 Installation Guide 48 Installation Procedure Overview Laser Notice ...
Page 100: ...ASR 5000 Installation Guide 84 Line Card Installation Installing the XGLC ...
Page 122: ...ASR 5000 Installation Guide 106 Cabling the Fast Ethernet 10 100 Line Card FLC2 Interfaces ...
Page 206: ...ASR 5000 Installation Guide 190 Removing and Installing SMC PC Cards Removing PC Cards ...
Page 212: ...ASR 5000 Installation Guide 196 Replacing the Chassis Air Filter Installing the Air Filter ...
Page 220: ...ASR 5000 Installation Guide 204 Replacing a Power Filter Unit What to do with the Failed PFU ...
Page 266: ...ASR 5000 Installation Guide 250 Safety Electrical and EMC Certifications Korean EMC ...
Page 270: ...ASR 5000 Installation Guide 254 Environmental Specifications Chassis Air Flow ...