1.  Dig a 150mm by 150mm trench both up-slope and down-slope of the area the matting is to be 

applied. Prepare the slope soil surface (raking, seeding and fertilising).

2.  Begin by placing the blanket a minimum of 300mm down-slope of the up-slope trench. Secure 

the blanket at the bottom of the trench with staples placed 300mm apart. Backfill and compact 

the trench. Apply seed, and fold the blanket over soil, secure with a row of staples placed 300mm 

apart across the width of the blanket (See Diagram A).

3.  Roll the blanket vertically down the slope. Secure using the appropriate staple pattern below, 

specified by slope (See staple patterns).

4.  Parallel blankets must be overlapped by a minimum of 100mm and secured with a row of staples 

approximately 1m apart (See Diagram B).

5.  Additional vertical blankets can be joined using a minimum 100mm overlapping or shingle 

style (See diagrams C) in the direction of the water flow. Connect the blankets by placing staples 

approximately 300mm apart across the width of the blankets.

6.  For maximum performance a check slot should be placed at 8m-12m intervals. Place a row of 

staples 100mm apart along the entire width of the slope. A second row should be placed 100mm 

below in a staggered pattern. Then continue with general installation (See diagrams D).

7.  The end of blanket must be secured in a 150mm by 150mm trench with a row of staples placed at 

300mm intervals (Diagram E).

SLOPE 

INSTALLATION

DETAIL

F

LOW

D

F

DIAGRAM

DIAGRAM

B

A

D

C

D

These guidelines are 

recommendations only.

Installations on steep slopes will 
require the correct safety gear.