FCA2X1U-FCA3X1U-FCA3X1UP
Installation Instructions
8
Figure 5
NOTE:
If rails must be installed over cable management holes
on column, cables must be routed prior to installing
rails onto quick connect bases. See Cable
Management section for details.
7.
Install two 5/16-18 x 3/4" button head flange screws (HH)
into the top holes on each quick connect base (Q). (See
Figure 6)
Figure 6
8.
Hang rails (J, K or L) into screws installed in previous step
to quick connect bases (Q). (See Figure 6)
IMPORTANT ! :
If installing the triple display rail (L),
install rail to left and center columns so that add-on rail
can be installed to right column. See Add-On Rail
Installation section for details.
9.
Install two 5/16-18 x 3/4" button head flange screws (HH)
into the lower holes on each quick connect base (Q) to
secure rails to quick connect bases. (See Figure 7)
10. Tighten all 5/16-18 x 3/4" button head flange screws (HH).
Figure 7
Add-On Rail Installation (FCA3X1 only)
1.
Install add-on rail (KK) to right column following instructions
in Rails Installation section.
2.
Use three #10-24 x 1 1/2" flat head cap screws (Z) to attach
add-on rail (KK) to display rail (L). (See Figure 8)
Figure 8
Complete installation of displays following LVM or LBM Series
installation instructions.
IMPORTANT ! :
Install displays to lower rails prior to
installing displays to upper rails. See LVM or LBM Series
installation instructions for further details regarding
acceptable and safe mounting orders.
(Q)
(HH) x 4
6
(P)
(HH) x 2
8
8
7
(Q)
(K or L)
(HH) x 2
9
(Z) x 3
2
(KK)