3. Assembly and Connection
The drilling-milling machine comes pre-assembled.
3.1 Extent of supply
When the drilling-milling machine is delivered, check immediately that the machine
has not been damaged during transport and that all components are included. Also
check that no fastening screws have come loose.
Compare the parts supplied with the information on the packaging list.
3.2 Transport
Warning!
Machine parts falling off forklift trucks or other transport vehicles could cause very
serious or even fata injuries. Follow the instructions and information on the transport
case:
•
Centers of gravity,
•
Suspension points,
•
Weights,
•
Means of transport to be used,
•
Prescribed shipping position.
Use of unstable lifting equipment and load-suspension devices that break under load
can cause very serious injury or even death.
Check that the lifting and load-suspension gear has sufficient load capacity and that
it is in perfect condition.
Observe the rules for preventing accidents.
Holds the load properly.
Never walk under suspended loads.
3.3 Storage
Improper storage may cause important parts to be damaged or destroyed.
Store packed or unpacked parts only under the intended environmental conditions.
Consult Chester UK if the machine or accessories have to be stored for a period of
over three months or under different environmental conditions than those given here.
3.4 Installation and assembly
The work area for operation, maintenance and repair work must not be hindered.
The mains plug of the drilling-milling machine must be freely accessible.
10
Summary of Contents for Champion 20VS