Installation
1. Remove the booster heater element cover.
2. Remove the paper insulator and
jumper bars from the heater terminals.
3.
Install the jumper bars for 1PH as shown, Fig. 17.
4.
Additional short jumper bars are stowed
with the new data plate.
5. Connect the wires to the terminals as shown.
6. Reinstall the paper insulator and the
booster heater element cover.
Rewire Wash Tank Heater Element for 1PH
1. Disconnect all power to the machine.
2. Remove front panel to access the power terminal block.
3.
Connect jumper wire (supplied be factory), Fig. 15.
between L2 and L3 on output side of terminal block
4. Connect power on L1 and L2 of the terminal block.
1 Phase 208-240/60/1
LINE IN
GRD
L1
L2
L1
L2
L3
JUMPER
Fig. 15 - Jumper wire
Convert DH6000 208-240VAC Only
From 3PH to 1PH Operation
NOTE:
The installer must contact the factory to receive the
jumper wire, jumper bars, and replacement data plate
before making the conversion.
1. Rewire tank heater wires according to Fig.16.
Rewire Booster Tank Heater Element for 1PH
1PH
L1
L2
L3
Fig. 16 - 1PH tank element connections
1PH
L3
L2
L1
Fig. 17 - 1PH booster element connections
Install Jumper Wire
10