Section B. Unit Setup
B.3
Packing List / Loose Parts
Inside the container you’ll find the following items packed along with the main machine
Lid Cage
Conveyer Catch Tray
Tool kit
Twist rinser (if ordered)
Spare parts package (if ordered)
Darex Manual “Evaluating and Controlling Double Seams Manual”
B.3.1
Moving Unit into Position
After removing bands and holding blocks securing canning machine to pallet base, use forklift (lift truck) to move
main unit into position (refer to unit footprint Figure 2 for clearances).
Protect stainless finish by placing wood on lifting forks to prevent metal-on-metal contact.
Spread forks so lifting points are as close to welded joints as possible to prevent bending cross supports.
Slide lifting forks under lower supports centered on balance fulcrum of unit which is located on center of the
machine.
Figure 5 Forklift moving Cask ACS into position
B.4
Initial Adjustments & Settings
Your Cask canning line has been factory tested prior to shipping to allow for trouble free installation by a Cask Technical
Representative at your site.
Your warranty period will also commence at the date of installation and commissioning by a Cask Technical Rep.
Prior to arrival of your Cask Technical Rep, you should complete the following initial machine setup:
•
Inspect overall machine shipping damage.
•
Level machine in final production position.
•
Have qualified electrician connect the machine to plant power (refer to C.4 Electrical Panel ).
•
Connect machine to compressed air supply (see Table 1).
•
Connect machine to plant CO2 system (see Table 1).