6 - MAINTENANCE
Connecting booster batteries
Make sure that the booster battery voltage corre-
sponds to the voltage system of the machine (
24
V
).
1.
Place the key of the battery master switch in
“O”
(off) position.
2.
Remove the terminal sleeves.
3.
Connect the positive
(+)
cable to the positive
(+)
terminal on the first machine battery.
4.
Connect the negative
(-)
cable to the negative
(-)
terminal on the second machine battery.
5.
Start the engine.
6.
Place the key of the battery master switch in
“I”
(on) position.
7.
Remove the booster battery negative
(-)
cable
and then the positive
(+)
cable.
8.
Install the terminal sleeves.
Belt tension
To check the belt tension proceed as follows:
1.
Stop the engine.
2.
Remove the key from the starter switch.
3.
Press the center of the belt with a finger with a
pressure of about
10 kg
(
22.0 lb
).
Deflection range (new part)
7.7 - 8.7 mm
(
0.303 - 0.343 in
)
Deflection range (reused part)
8.3 - 9.3 mm
(
0.327 - 0.366 in
)
NOTICE:
if the engine runs with the belt slack, the belt can
slip in its housing and cause the engine to overheat or the
battery to receive insufficient charge.
NOTE:
check that there is no damage due to wear on the
pulley or the belt. Check that the belt is positioned correctly
in the pulley groove. Replace the belt if it is stretched,
cracked, or frayed.
SMIL13CEX2774AB
1
SMIL13CEX2775AB
2
6-40
Summary of Contents for CX75C SR
Page 14: ...1 GENERAL INFORMATION Machine components SMIL13CEX2515FB 1 SMIL13CEX2906FB 2 1 8 ...
Page 33: ...2 SAFETY INFORMATION SMIL13CEX2925HB 4 2 17 ...
Page 48: ...2 SAFETY INFORMATION 2 32 ...
Page 230: ...6 MAINTENANCE 6 84 ...
Page 241: ...8 SPECIFICATIONS Work range standard model SMIL13CEX2899HB 5 8 9 ...
Page 243: ...8 SPECIFICATIONS Work range blade type SMIL13CEX2900HB 6 8 11 ...
Page 248: ...8 SPECIFICATIONS 8 16 ...
Page 255: ......