START-UP CHECKLIST
(Fill out this form on Start-Up and file in job folder)
I. PRELIMINARY INFORMATION
09XC UNIT:
MODEL NO. ____________________ SERIAL NO. ____________________
FIELD-INSTALLED ACCESSORIES: _____________________________________________________________________
START-UP DATE: ______________________________________
II. PRE-START-UP:
VERIFY ALL SHIPPING MATERIALS HAVE BEEN REMOVED FROM THE UNIT
IS THERE ANY SHIPPING DAMAGE? ________________ IF SO, WHERE ________________
_____________________________________________________________________________________________________
WILL THIS DAMAGE PREVENT UNIT START-UP?
(Y/N) _______
CHECK POWER SUPPLY. DOES IT AGREE WITH UNIT? (Y/N) _______
HAS THE GROUND WIRE BEEN CONNECTED?
(Y/N) _______
HAS THE CIRCUIT PROTECTION BEEN SIZED AND INSTALLED PROPERLY? (Y/N) _______
ARE THE POWER WIRES TO THE UNIT SIZED AND INSTALLED PROPERLY? (Y/N) _______
HAVE CONDENSER FAN AND MOTOR PULLEYS BEEN CHECKED FOR PROPER
ALIGNMENT AND DO THE FAN BELTS HAVE PROPER TENSION? (Y/N) _______
HAS CORRECT FAN ROTATION ON CONDENSER BEEN CONFIRMED?
(Y/N) _______
ARE PROPER AIR FILTERS IN PLACE AND ARE FILTERS CLEAN? (Y/N) _______
VERIFY UNIT IS INSTALLED WITHIN LEVELING TOLERANCES
(Y/N) _______
CONTROLS
HAVE CONTROL CONNECTIONS BEEN MADE AND CHECKED?
(Y/N) _______
ARE ALL WIRING TERMINALS (including main power supply) TIGHT? (Y/N) _______
PIPING
HAVE LEAK CHECKS BEEN MADE AT COMPRESSOR, CONDENSER, EVAPORATOR, TXVs
(Thermostatic Expansion Valves), SOLENOID VALVES, FILTER DRIERS, AND FUSIBLE PLUGS
WITH A LEAK DETECTOR? (Y/N) _______
LOCATE, REPAIR, AND REPORT ANY LEAKS
HAVE ALL COMPRESSOR SERVICE VALVES BEEN FULLY OPENED (BACKSEATED)? (Y/N) _______
HAVE LIQUID LINE SERVICE VALVES BEEN OPENED? (Y/N) _______
IS THE OIL LEVEL IN THE COMPRESSOR CRANKCASE ON THE UNIT IN VIEW IN THE
COMPRESSOR SIGHT GLASS (IF APPROPRIATE)? (Y/N) _______
HAS CONDENSER PRESSURE RELIEF BEEN PROVIDED? (Y/N) _______
NOTE: To avoid injury to personnel and damage to equipment or
property when completing the procedures listed in this start-up
checklist, use good judgment, follow safe practices, and adhere
to the safety considerations/information as outlined in preceding
sections of this Installation, Start-Up, and Service document.