4 - COMPONENTS

4.1 - Fan motors LEC

4.1.1 - Procedure for dismantling of the motor (Fig. 12)

CAUTION:  Before  any  intervention  on  this  product,  it  is 

imperative to cut the power supply to the unit.

In  the  case  of  malfunctioning  of  the  fan  motor,  the  complete 

assembly of the fan motor must be dismantled and replaced:

 

-

Unhook the ATM from its suspension support by following 

the procedure indicated (See 3.3 – Procedure for dismantling 

of the ATM).

 

-

Open the filter access door (Fig. 12a).

 

-

Unscrew and then remove the side plate (Fig.12.b) of the 

ATM fixed with Torx T20 star screws (side opposite to the 

non-removable plate).

 

-

Disconnect the power supply cables of the fan motor (quick 

power and control connectors).

 

-

The fan motor is fixed to the unit with Torx T20 star screws, 

unscrew these screws from the outside.  (Fig.12c).

 

-

Remove the fan motor (Fig.12d) from the side of the removed 

plate.

 

-

Replace  the  fan  motor  and  proceed  with  reassembly  by 

applying the procedure in reverse order.

NOTE: Be careful not to touch the turbines while dismantling 

the fan motor, balancing may be adversely affected.

 

-

In the case of an optional electric battery:

On 42GR ATM Size 19: the electric battery is located in the 

suction eye of the fan motor. Unscrew the electric battery 

support in order to isolate the fan motor. 

On 42GR ATM Size 29: the electric battery is placed in the 

discharge suction eye of the fan motor. Mark the number of 

components  connected  to  the  electric  battery,  and  then 

disconnect these electric wires as well as the quick power 

supply connector from the electric battery. Do not let the wires 

touch each other. Then, lift the electric battery from its support 

from the outside in order to reach the fixing screws of the fan 

motor.

 

-

Remove the fan motor (Fig.12d) from the side of the removed 

plate.

 

-

Replace  the  fan  motor  and  proceed  with  reassembly  by 

applying the procedure in the reverse order.

4.1.2 - Fan cabling

4.1.2.1 - Variable speed LEC - naked wires

See Fig.13.

4.1.2.2 - Variable speed LEC - NTC regulator (optional)

The electrical connection to a 230 V AC supply of the fan motor 

as well as that of the 0-10V DC control signal are made in the 

factory in the NTC regulator.

CAUTION: For the supply of the NTC, the connection of the 

various inlets / outlets and the adjustment of the regulator: 

refer to the installation and operation manual of the NTC.

4.2 - Optional electric battery

CAUTION: Before any intervention, it is imperative to cut the 

electrical power supply of the unit.

In the case of malfunctioning of the electric battery the latter must 

be  replaced.  This  replacement  procedure  is  slightly  different 

depending on the size of the 42GR ATM: Size 19 or 29. 

IMPORTANT: When the electric battery is powered, do not 

touch the metallic components which are turned on.

4.2.1 - Procedure for replacement of the electric 

battery - 42GR ATM Size 19 (Fig. 14)

For the Size 19 42GR ATM, the electric battery is located in the 

suction eye of the fan motor.

CAUTION:  Before  any  intervention  on  this  product,  it  is 

imperative to cut the electrical power supply of the unit.

 

-

Unhook the ATM from its suspension support by following 

the procedure indicated (See 3.3 – Procedure for dismantling 

the ATM).

 

-

Open the filter access door (Fig. 12a).

 

-

Unscrew and then remove the side plate of the ATM fixed 

with Torx T20 star screws (side opposite to the non-removable 

plate) (Fig.14a).

 

-

Mark the number of components connected to the electric 

battery, and then disconnect these electric wires as well as 

the quick power supply connector from the electric battery. 

Do not let the wires touch each other.

 

-

Unscrew the fixing screws from the electric battery support 

(Fig.14b).

 

-

Remove the electric battery (Fig. 14c) from its support.

 

-

Replace the electric battery and proceed with reassembly by 

applying the procedure in the reverse order.

4.2.2 - Procedure with replacement of the electric 

battery - 42GR ATM Size 29 (Fig. 15)

For  the  size  29  42GR ATM,  the  electric  battery  is  placed  in 

discharge suction eye of the fan motor.

 

-

Unhook the ATM from its suspension support by following 

the procedure indicated (See 3.3 - Procedure for dismantling 

the ATM).

 

-

Mark the number of components connected to the electric 

battery, and then disconnect these electric wires as well as 

the quick power supply connector from the electric battery. 

Do not let the wires touch each other.

 

-

Remove  the  electric  battery  (Fig.  15a)  from  its  support 

(Fig.15b).

 

-

Replace the electric battery and proceed with reassembly by 

applying the procedure in the reverse order.

CAUTION: The Carrier type B and D electronic thermostats 

are  provide  with  an  8 Amps  electric  battery  relay.  Carrier 

requires an additional protective relay for the electric coils 

above 1600 Watts.
CAUTION:  In  case  of  regulator  provided  by  the  customer, 

Carrier  recommends  the  installation  of  an  additional 

protective relay corresponding to the capacity of the electric 

battery.

4.3 - Water coils

4.3.1 - Procedure for dismantling the water battery 

(Fig. 16)

CAUTION:  Before  any  intervention,  it  is  imperative  to  cut 

electrical power supply to the device.

 

-

Unhook the ATM from its support by following the procedure 

indicated (See 3.3 – Procedure for dismantling the ATM).

 

-

Open the filter access door (Fig. 16a) and remove the filter. 

Mark  the  direction  of  the  filter:  the  side  with  the  seal  is 

positioned against the inner plate of the ATM.

 

-

Unscrew the side plate of the ATM (Fig. 16b) fixed with Torx 

T20 star screws (side opposite to the non-removable plate).

 

-

Remove the valve casings (Fig. 16c) fixed with Torx T20 star 

fixing screws.

 

-

Disconnect the hydraulic hoses by unscrewing the G 1/2” 

rotating nuts. Drain the water from the battery into a container.

 

-

Disconnect the servomotors taking care to mark the cold and 

hot valves.

 

-

Remove  the  2-channel  or  3-channel  water  flow  regulator 

valve body. Depending on the adjustment of the device, the 

coupling of the 3-channel valve can be provided with a hot/ 

cold reverser, do not dismantle it.

15

Summary of Contents for Idrofan 42GR ATM

Page 1: ...I N S TA L L AT I O N I N S T R U C T I O N S Original document AIR TREATMENT MODULE 42GR ATM...

Page 2: ......

Page 3: ...ONSIDERATIONS 12 2 1 General points 12 2 2 Protection against electrocution 12 2 3 General recommendations for installation 12 2 4 Recommendation regarding the regulation 12 2 5 Regulations 12 3 INSTA...

Page 4: ...B C D 4a 4b 4c E 2000 125 12 5 250 480 518 480 11 19 9 500 500 500 250 5a 125 F 4...

Page 5: ...6k 6f 6f 6f 6e 6i 6d 6b 6a 6g 6h 6c E B A C D 6j 6e A B C D E F 42 GR T19 334 585 895 1138 805 12 5 42 GR T29 416 585 895 1138 805 12 5 G 7b 7c 7a 22 17 50 15 50 30 50 100 mm H 5...

Page 6: ...B A D 8a C L E G H I J F K J A B C D E F G H I J K L 42 GR T19 90 107 137 125 230 159 93 58 250 93 177 250 42 GR T29 90 147 267 125 230 199 122 170 420 120 160 250 B A D 9a C L E G H I J F K A C E F...

Page 7: ...E F G H I J 42 GR T19 250 402 198 674 128 742 344 600 183 75 125 42 GR T29 420 402 198 674 128 742 344 600 183 75 125 11a 11b 11c L B C 450 max J H G F I D E C L 12c 12b 12d 12a M 0 10 V 230 V N E B...

Page 8: ...P 15a 15b O 14c 14b 14a 16b 16c 16e 16d 16a 16f Q 17c 17b 17a 17d R 8...

Page 9: ...MR60 17 60 4 4 4 4 MR75 21 75 4 3 4 3 MR85 24 85 3 3 3 2 MR90 25 90 3 2 2 2 MR100 28 100 2 1 2 1 MR105 29 105 2 1 1 1 MR110 31 110 1 1 1 1 MR120 33 120 3 3 MR130 36 130 2 1 MR140 39 140 1 1 MR160 44...

Page 10: ...12d Fan motor N LEC vitesse variable wires nus 1 Phase 230 V brown wire 2 Neutral 230 V blue wire 3 Earthing green and yellow wire 4 0 10 V yellow wire 5 GND blue wire O Replacement of the electric b...

Page 11: ...ling and corrosion The water circuit must include components required for the treatment of water lters additives intermediate exchangers purges vents isolating valves etc depending on the results of t...

Page 12: ...blue brown green yellow and its cross section and type must comply with the specifications set out by the applicable EN or IEC standard Refer to the selection sheet or the name plate to determine the...

Page 13: ...Then connect the hydraulic hoses Connect the condensate drains of the ATM Fig 7 using a fastener for exible tube of inner 16 mm Fig 7a To avoid the emergence of odour it is MANDATORY to install a siph...

Page 14: ...ded with check valves provide a container making it possible to drain the battery Disconnect the condensate drain pipes Disconnect the fresh air supply in the case where it is xed to the ATM See 3 2 2...

Page 15: ...the Size 19 42GR ATM the electric battery is located in the suction eye of the fan motor CAUTION Before any intervention on this product it is imperative to cut the electrical power supply of the unit...

Page 16: ...of regulator enables bringing in fresh air ow from 30 m3 h 8 3 l s 10 20 Procedure for replacement of the xed constant fresh air ow regulator Disconnect the exible fresh air duct Fig 11a from the fer...

Page 17: ...e body on the battery put new seals Reinstall the servomotors taking care to see that they are correctly calamped onto the valve body Reconnect the hydraulic hoses by screwing back the G 1 2 rotating...

Page 18: ...t A TOR 230V C 3 pts 230V Digit 13 Without Probe C Change over Digit 16 W WC VARIABLE Digit 14 A F5 K F6 P F7 Active carbon S Filter UVPCO Digit 15 Without X SPECIAL J Only ferrule without regulator K...

Page 19: ......

Page 20: ...2021 replaces No 14243 03 2014 The manufacturer reserves the right to modify the product specifications without prior notice Manufacturer Carrier S C S Rte de Thil 01120 Montluel France Printed in th...

Reviews: