Use refrigeration grade tubing. Service valves are closed from
factory and ready for brazing. After wrapping service valve with a

wet cloth, braze sweat connections using industry accepted
methods and materials. Consult local code requirements.

Refrigerant tubing and indoor coil are now ready for leak testing.

This check should include all field and factory joints.

Table 1 – Refrigerant Connections and Recommended Liquid

and Vapor Tube Diameters (In.)

UNIT SIZE (SERIES)

LIQUID

RATED VAPOR

up to 80 ft. (24.38 m)*

Connection

& Tube

Diameter

Connection

Diameter

Tube

Diameter

18, 24

3/8

5/8

5/8

30, 36

3/8

3/4

3/4

42, 48

3/8

7/8

7/8

60

3/8

7/8

1---1/8

Notes

:

1. Tube diameters are for total equivalent lengths up to 80 ft. (24.38 m)
2. Do not apply capillary tube or fixed orifice indoor coils to these units.
* For Tubing Set lengths between 80 and 200 ft. (24.38 and 60.96 m)

horizontal or 20 ft. (6.10 m) vertical differential (250 ft. (76.2 m)Total

Equivalent Length), refer to the Longline Guideline--- Air Conditioners

and Heat Pumps using R---22

Install Liquid--Line Filter Drier Indoor

CAUTION

!

UNIT DAMAGE HAZARD

Failure to follow this caution may result in equipment

damage or improper operation.
1. Installation of filter drier in liquid line is required.
2. Filter drier must be wrapped in a heat--sinking material

such as a wet cloth while brazing.

Refer to Fig. 3 and install filter drier as follows:

1. Braze 5--in. liquid tube to the indoor coil.
2. Wrap filter drier with damp cloth.
3. Braze filter drier to above 5--in. (127 mm) liquid tube.

Flow arrow must point towards indoor coil.

4. Connect and braze liquid refrigerant tube to the filter drier.

A05178

Fig. 3 -- Liquid Line Filter Drier

Evacuate Refrigerant Tubing and Indoor Coil

CAUTION

!

UNIT DAMAGE HAZARD

Failure to follow this caution may result in equipment

damage or improper operation.
Never use the system compressor as a vacuum pump.

Refrigerant tubes and indoor coil should be evacuated using the

recommended deep vacuum method of 500 microns. The alternate
triple evacuation method may be used (see triple evacuation

procedure in service manual). Always break a vacuum with dry
nitrogen.

Deep Vacuum Method

The deep vacuum method requires a vacuum pump capable of

pulling a vacuum of 500 microns and a vacuum gage capable of
accurately measuring this vacuum depth. The deep vacuum method

is the most positive way of assuring a system is free of air and

liquid water. A tight dry system will hold a vacuum of 1000
microns after approximately 7 minutes. See Fig. 4.

500

MINUTES

0

1

2

3

4

5

6

7

1000

1500

LEAK IN

SYSTEM

VACUUM TIGHT

TOO WET
TIGHT

DRY SYSTEM

2000

MI

CRONS

2500

3000

3500

4000

4500

5000

A95424

A95424

Fig. 4 -- Deep Vacuum Graph

Final Tubing Check

IMPORTANT

: Check to be certain factory tubing on both indoor

and outdoor unit has not shifted during shipment. Ensure tubes are
not rubbing against each other or any sheet metal or wires. Pay
close attention to feeder tubes, making sure wire ties on feeder
tubes are secure and tight.

24AC

S

Summary of Contents for Comfort 24ACS

Page 1: ... switch Lock out and tag switch with a suitable warning label INSTALLATION INSTRUCTIONS NOTE In some cases noise in the living area has been traced to gas pulsations from improper installation of equipment 1 Locate unit away from windows patios decks etc where unit operation sound may disturb customer 2 Ensure that vapor and liquid tube diameters are appropriate for unit capacity 3 Run refrigerant...

Page 2: ...Relieve pressure and recover all refrigerant before system repair or final unit disposal Use all service ports and open all flow control devices including solenoid valves Federal regulations require that you do not vent refrigerant to the atmosphere Recover during system repair or final unit disposal CAUTION UNIT DAMAGE HAZARD Failure to follow this caution may result in equipment damage or improp...

Page 3: ... in liquid tube to the indoor coil 2 Wrap filter drier with damp cloth 3 Braze filter drier to above 5 in 127 mm liquid tube Flow arrow must point towards indoor coil 4 Connect and braze liquid refrigerant tube to the filter drier A05178 Fig 3 Liquid Line Filter Drier Evacuate Refrigerant Tubing and Indoor Coil CAUTION UNIT DAMAGE HAZARD Failure to follow this caution may result in equipment damag...

Page 4: ...round connection in control box for safety Connect power wiring to contactor as shown in Fig 5 DISCONNECT PER N E C AND OR LOCAL CODES CONTACTOR GROUND LUG FIELD GROUND WIRING FIELD POWER WIRING BLUE 3 PHASE ONLY A94025 Fig 5 Line Connections Connect Control Wiring Route 24 v control wires through control wiring grommet and connect leads to control wiring See Fig 6 Refer to Installation Instructio...

Page 5: ...igerant line lengths 80 ft 24 38 m or less allow system to operate in cooling mode at least 15 minutes If conditions are favorable check system charge by subcooling method If any adjustment is necessary adjust charge slowly and allow system to operate for 15 minutes to stabilize before declaring a properly charged system If the indoor temperature is above 80_F 26 67_C and the outdoor temperature i...

Page 6: ... FAN A02326 LEGEND 24 V FACTORY WIRING 24 V FIELD WIRING FIELD SPLICE CONNECTION CONTACTOR C A97368 Fig 6 Generic Wiring Diagrams See Thermostat Installation Instruction for specific unit combinations Copyright 2008 Carrier Corp S 7310 W Morris St S Indianapolis IN 46231 Printed in U S A Edition Date 04 08 Manufacturer reserves the right to change at any time specifications and designs without not...

Reviews: