background image

6

The information on operating inspections given in annex 
C of standard EN 378 can be used if no similar criteria 
exist in the national regulations.

While working in the fan area, especially when grilles or 
casings are removed, disconnect the fan power supply to 
prevent their automatic restart.

Protection device checks:
• 

If no national regulations exist, check the protection 
devices on site in accordance with standard EN 378: 
Once a year for the high-pressure switches, every five 
years for external relief valves.

The company or organisation that conducts a pressure 
switch test must establish and implement detailed 
procedures for:

Safety measures

Measuring equipment calibration

Validating operation of protective devices

Test protocols

Recommissioning of the equipment.

Consult Carrier Service for this type of test. Carrier 
mentions here only the principle of a test without 
removing the pressure switch:

Verify and record the set-points of pressure switches 
and relief devices (valves and possible rupture discs)

Be ready to switch-off the main disconnect switch of 
the power supply if the pressure switch does not 
trigger (avoid over-pressure or excess gas in case of 
valves on the high-pressure side with the recovery 
condensers)

Connect a pressure gauge protected against pulsations 

(filled with oil with maximum pointer if mechanical), 

preferably calibrated (the values displayed on the user 
interface may be inaccurate in an instant reading 
because of the scanning delay applied in the control)

Complete an HP Test as provided by the software 
(refer to the Control IOM for details).

If the machine operates in a corrosive environment, inspect 
the protection devices more frequently. 

Regularly carry out leak tests and immediately repair any 
leaks. Ensure regularly that the vibration levels remain 
acceptable and close to those at the initial unit start-up.

Before opening a refrigerant circuit, purge and consult the 
pressure gauges.

Change the refrigerant after an equipment failure, following 
a procedure such as the one described in NF E29-795 or 
carry out a refrigerant analysis in a specialist laboratory.

Plug all openings whenever the refrigerant circuit is opened 
for up to one day. For longer openings place a nitrogen 
charge in the circuit.

Units with option 231 are equipped with capacitor 
batteries with a discharge time of five (5) minutes after 
disconnecting the power. After disconnecting the power to 
the control box, wait five minutes before opening the 
control box. Before any intervention, verify that there is no 
voltage present at any accessible conducting parts of the 
power circuit.

Operating checks:
IMPORTANT INFORMATION REGARDING THE 
REFRIGERANT USED:
• 

This product contains fluorinated greenhouse gas 
covered by the Kyoto protocol.

 

Fluid type: R134a

 

Global Warming Potential (GWP): 1430

CAUTION: 

1.  Any intervention on the refrigerant circuit of this 

product should be performed in accordance with the 
applicable legislation. In the EU, the regulation is 
called F-Gas, N°517/2014

2.  Ensure that the refrigerant is never released to the 

atmosphere during installation, maintenance or 
equipment disposal. 

3.  The deliberate gas release into the atmosphere is not 

allowed.

4.  If a refrigerant leak is detected, ensure that it is 

stopped and repaired as quickly as possible.

5.  Only a qualified and certified personnel can perform 

installation operations, maintenance, refrigerant 
circuit leak test as well as the equipment disposal and 
the refrigerant recovering.

6.  The gas recovery for recycling, regeneration or 

destruction is at customer charge.

7.  Periodic leak tests have to be carried out by the 

customer or by third parties. The EU regulation set 
the periodicity here after:

System WITHOUT 

leakage detection

No 

check

12 months

6 months

3 months

System WITH leakage 

detection

No 

check

24 months

12 months

6 months

Refrigerant charge/

circuit (CO

2

 equivalent)

 < 5 

tonnes

5 ≤ charge 

 

< 50 tonnes

50 ≤ charge 

 

< 500 tonnes

Charge  

> 500 

tonnes*

Refrigerant 

charge/

circuit (kg)

R134a 

(GWP 

1430)

Charge  

< 3.5 kg

3.5 ≤ charge 

< 34.9 kg

34.9 ≤ charge 

< 349.7 kg

Charge  

> 349.7 kg

R407C 

(GWP 

1774)

Charge 

< 2.8 kg

2.8 ≤ charge 

< 28.2 kg

28.2 ≤ charge 

< 281.9 kg

Charge  

> 281.9 kg

R410A 

(GWP 

2088)

Charge  

< 2.4 kg

2.4 ≤ charge 

< 23.9 kg

23.9 ≤ charge 

< 239.5 kg

Charge  

> 239.5 kg

HFO’s : 

R1234ze

No requirement

* From 01/01/2017, units must be equipped with a leakage detection system

8.  A logbook must be established for equipments subject 

to periodic leak tests. It should contain the quantity 

and the type of fluid present within the installation 
(added and recovered), the quantity of recycled fluid, 

regenerated or destroyed, the date and output of the 
leak test, the designation of the operator and its 
belonging company, etc.

9.  Contact your local dealer or installer if you have any 

questions.

Summary of Contents for Aquaforce 30XA Series

Page 1: ...INSTALLATION OPERATION AND MAINTENANCE INSTRUCTIONS Air Cooled Screw Chillers 30XA A Nominal cooling capacity 267 1682 kW 50 Hz Unit with options 23A 258 and 279 Original document...

Page 2: ...XA 1702 module 1 2 MCHE heat exchanger standard and 30XA 1702 module 1 2 Cu Al heat exchanger option 254 255 15 3 11 30XA 1702 module 2 2 MCHE heat exchanger standard and 30XA 1702 module 2 2 Cu Al he...

Page 3: ...control 42 9 8 Heat reclaim operation 42 9 9 Condenser pump selection 42 9 10 Frost protection 43 10 FANS WITH AVAILABLE PRESSURE OPTION 10 43 11 MAJOR SYSTEM COMPONENTS AND OPERATION DATA 43 11 1 Dir...

Page 4: ...e unit The units can also be lifted with slings using only the designated lifting points marked on the unit These units are not designed to be lifted from above Use slings with the correct capacity an...

Page 5: ...d documentation supplied with the products These units are intended to be stored and operated in an environment where the ambient temperature must be not less than the lowest allowable temperature ind...

Page 6: ...option 231 are equipped with capacitor batteries with a discharge time of five 5 minutes after disconnecting the power After disconnecting the power to the control box wait five minutes before opening...

Page 7: ...ny spills from the skin with soap and water If liquid refrigerant enters the eyes immediately and abundantly flush the eyes with water and consult a doctor The accidental releases of the refrigerant d...

Page 8: ...replacement Consult the list of replacement parts that corresponds to the specification of the original equipment Do not drain water circuits containing industrial brines without informing the technic...

Page 9: ...ever push or lever on any of the enclosure panels of the unit Only the base of the unit frame is designed to withstand such stresses If a unit includes a hydronic module options 116B C F G the hydroni...

Page 10: ...nit For options 5 6 100A 100C 107 refer to the certified drawing Air outlet do not obstruct Power supply and control connection Control circuit connection for option 158 NOTES Drawings are not contrac...

Page 11: ...ions 5 6 100A 100C 107 refer to the certified drawing Air outlet do not obstruct Power supply and control connection Control circuit connection for option 158 NOTES Drawings are not contractually bind...

Page 12: ...ons 5 6 100A 100C 107 refer to the certified drawing Air outlet do not obstruct Power supply and control connection Control circuit connection for option 158 NOTES Drawings are not contractually bindi...

Page 13: ...C NOTES Drawings are not contractually binding Before designing an installation consult the certified dimensional drawings available on request For the positioning of the fixing points weight distrib...

Page 14: ...ler installation and 3 13 Distance to the wall of this document to determine the space required 3 9 30XA 1402 1502 module 2 2 MCHE heat exchanger standard and 30XA 1402 1502 module 2 2 Cu Al heat exch...

Page 15: ...or option 158 NOTES Drawings are not contractually binding Before designing an installation consult the certified dimensional drawings available on request For the positioning of the fixing points wei...

Page 16: ...t your Carrier distributor to evaluate the various possible arrangements In certain situations an accessory supplied loose at the time of purchase can be added 3 13 Distance to the wall To ensure corr...

Page 17: ...8 20 8 20 8 23 5 23 5 23 5 23 5 23 5 23 5 Capacity control Touch Pilot electronic expansion valve EXV Minimum capacity 15 15 15 15 15 15 15 15 15 15 15 15 15 Condensers All aluminium microchannel heat...

Page 18: ...D kg 63 teqCO2 90 1 Oil charge Circuit A l 27 6 27 6 27 6 27 6 27 6 36 36 27 6 27 6 27 6 Circuit B l 27 6 27 6 27 6 36 36 36 36 27 6 27 6 23 5 Circuit C l 27 6 27 6 27 6 Circuit D l 23 5 Capacity con...

Page 19: ...5 23 5 23 5 23 5 23 5 27 6 Circuit C l Circuit D l Capacity control Touch Pilot electronic expansion valve EXV Minimum capacity 15 15 15 15 15 15 15 15 15 15 15 15 Condensers Copper aluminium coil Fa...

Page 20: ...screw compressors 50 r s Circuit A 1 1 1 1 1 1 1 1 Circuit B 1 1 1 1 1 1 1 1 Circuit C 1 1 1 Circuit D 1 Oil charge Circuit A l 27 6 27 6 36 36 36 27 6 27 6 27 6 Circuit B l 27 6 36 36 36 36 27 6 27...

Page 21: ...3 1039 1103 1118 1125 1143 Cosine Phi maximum 0 86 0 87 0 86 0 87 0 87 0 87 0 86 0 87 0 87 Cosine Phi nominal 0 85 0 85 0 85 0 86 0 87 0 87 0 86 0 85 0 85 Maximum power input Circuit 1 kW 359 420 182...

Page 22: ...60 Circuit 2 A 772 772 772 772 587 587 760 Option 81 A 1031 1047 1113 1128 1122 1133 Cosine Phi maximum 0 85 0 85 0 86 0 86 0 87 0 87 0 87 0 86 0 86 0 86 Cosine Phi nominal 0 84 0 84 0 84 0 84 0 84 0...

Page 23: ...772 772 845 865 761 Circuit 2 A 772 772 772 772 587 587 761 Option 81 A 1023 1039 1103 1118 1125 1143 Cosine Phi maximum 0 87 0 86 0 87 0 87 0 87 0 86 0 87 0 87 Cosine Phi nominal 0 85 0 85 0 86 0 87...

Page 24: ...t 1 A 860 587 587 772 772 845 860 760 Circuit 2 A 772 772 772 772 587 587 760 Option 81 A 1031 1047 1113 1128 1122 1133 Cosine Phi maximum 0 86 0 86 0 87 0 87 0 87 0 86 0 86 0 86 Cosine Phi nominal 0...

Page 25: ...characteristics used for the operation of the machines 1 Environment Environment as classified in EN 60364 corresponds to IEC 60364 Outdoor installation Ambient temperature range from 20 C to 55 C Alt...

Page 26: ...at full load and nominal voltage 86 1 88 6 88 6 90 1 91 3 91 3 1 Nominal efficiency at 75 rated load and nominal voltage 86 3 88 5 88 5 89 7 91 4 91 4 1 Nominal efficiency at 50 rated load and nominal...

Page 27: ...lator switch are designed for the number and type of wires listed in column 2 of the table on the next page The calculations are based on the maximum machine current see electrical data tables The cal...

Page 28: ...LPE Cu 904 2 x 240 2 x 185 205 XLPE Cu Not compatible 902 2 x 240 2 x 185 205 XLPE Cu Not compatible 1002 4 x 300 2 x 240 205 XLPE Cu 4 x 185 320 XLPE Cu Circuits A and B C common routing 1112 2 x 240...

Page 29: ...culated as shown in the diagram For minimum chilled water flow rate 1 Evaporator 2 Recirculation 6 3 Maximum chilled water flow units without hydronic module The maximum chilled water flow is shown in...

Page 30: ...buffer tank Bad Bad Good Good 6 6 Maximum system water volume Units with hydronic module incorporate an expansion tank that limits the water volume The table below gives the maximum loop volume for pu...

Page 31: ...1 702 2 752 3 802 4 854 852 5 904 902 6 1002 7 1112 8 1212 9 1312 10 1382 11 1402 12 1502 13 1702 Water flow rate l s Pressure drop kPa 1 2 4 5 6 9 8 10 3 7 11 13 12 100 100 10 10 10 100 10 252 302 35...

Page 32: ...ible with the materials and the water circuit coating The use of different metals on hydraulic piping could generate eletrolytic pairs and consequently corrosion Verify then the need to install sacrif...

Page 33: ...tions 5 6 and 100A Nominal diameter in 5 6 6 6 6 6 8 5 8 5 6 6 Actual outside diameter mm 141 168 3 168 3 168 3 168 3 168 3 219 1 141 3 219 1 141 3 168 3 168 3 Option 100C Nominal diameter in 6 8 Actu...

Page 34: ...re of 10 K below the lowest temperature likely to occur at the installation site If the unit is not used for an extended period it is recommended to drain it and as a safety precaution add ethylene gl...

Page 35: ...required kPa abs Water flow rate l s 7 7 2 Net positive suction head NPSH required hydronic module option Size the hydronic circuit to ensure a net positive suction head that is higher than or equal...

Page 36: ...separator 5 Principal electronic expansion valve EXV 6 Pressure and temperature measurement to calculate the sub cooling upstream of the pump 7 Motorised two way bypass valve 8 Free cooling expansion...

Page 37: ...nit The sealing joints are in the control box The temperature sensors and the condenser flow switch are wired and fixed in the machine They must be installed as described in the chapter Condenser wate...

Page 38: ...eight distribution and centre of gravity coordinates please refer to the dimensional drawings If the installation includes several units or if this these is are close to walls please refer to chapters...

Page 39: ...weight distribution and centre of gravity coordinates please refer to the dimensional drawings If the installation includes several units or if this these is are close to walls please refer to chapte...

Page 40: ...and centre of gravity coordinates please refer to the dimensional drawings If the installation includes several units or if this these is are close to walls please refer to chapters 3 11 Multiple chi...

Page 41: ...enser Legend 1 Heat reclaim condenser 2 Entering water temperature sensor supplied 3 Leaving water temperature sensor supplied 4 Condenser water flow switch supplied 5 Three way valve not supplied 9 4...

Page 42: ...om heat exchange at the air condenser to heat exchange at the water condenser and vice versa is ensured by motorised two way valves located upstream of the air and water condensers Setpoint C Condense...

Page 43: ...eral Monitoring during operation re qualification re testing and re testing dispensation Follow the regulations on monitoring pressurised equipment It is normally required that the user or operator se...

Page 44: ...oling of the rest of the flow that penetrates the evaporator via the prin cipal EXV This permits increasing the cooling capacity of the system as well as its efficiency 11 3 High pressure safety switc...

Page 45: ...on the compressor economiser discharge and suction lines ATTENTION The compressor suction valve must be used without pressure difference at the terminals If there is a pressure difference leak tightne...

Page 46: ...702 904 1 1 1 4 1 5 1 2 1 3 1 6 2 3 2 6 2 2 2 5 2 1 2 4 1 1 1 5 1 6 1 2 1 3 1 7 1 4 1 8 2 6 2 2 2 5 2 1 2 4 2 3 30XA 1112 1 1 1 5 1 6 1 2 1 3 1 7 1 4 1 8 2 7 2 5 2 8 2 4 2 7 2 5 2 3 2 2 2 6 2 1 2 6 3...

Page 47: ...pplementary water outlet temperature sensor kit to be field installed allowing master slave operation of two units connected in parallel Optimised operation of two chillers connected in parallel with...

Page 48: ...insulation of the evaporator entering leaving refrigerant lines with flexible anti UV insulant Prevents condensation on the evaporator entering leaving refrigerant lines 252 1702 Low noise level 257 S...

Page 49: ...ntion on the refrigerant circuit handling refrigerant Changing of parameters set at the factory application change Removal or dismantling of the HVAC unit Any intervention due to a missed established...

Page 50: ...l 6 1 Torque application to tighten the lug 2 Avoid contact between the two nuts 3 Lug tightening nut 4 Flat lug 5 Counter nut 6 Terminal tightening nut 7 Isolator 13 5 Tightening torques for the main...

Page 51: ...the coil surface or wedged between the chassis and the supports Provide personal protection equipment including safety glasses and or a face mask waterproof clothing and safety gloves It is recommend...

Page 52: ...sure drop across the filter can be determined by measuring the pressure at the filter service port and the oil pressure port The difference in these two pressures will be the pressure drop across the...

Page 53: ...g has been sized and installed properly Unit ground wire has been connected Electrical circuit protection has been sized and installed properly All terminals are tight All chilled water valves are ope...

Page 54: ...he chiller is not switched on until corrective measures have been taken Check cooler water loop Water loop volume litres Calculated volume litres 3 25 litres nominal kW capacity for air conditioning 6...