The tube end must stay bottomed in the service valve during
final assembly to ensure proper seating, sealing, and rigidity.

MECHANICAL FITTING REPAIR

To replace damaged ferrule or tubing proceed as follows.

1. Attach gages to service valves.

2. Close liquid service valve and operate unit to pump refrigerant

charge into condenser coil.

3. When suction pressure reaches 5 psig, shut unit off. Do not

operate unit in a vacuum.

4. Close suction service valve and recover refrigerant in tubing.

5. Back-off locknut and ferrule onto tube.

6. Remove damaged part of tubing using tubing cutter. Repeat

installation procedure previously outlined using new ferrule.

7. Evacuate tubing set and indoor coil. Check for leaks.

8. Open service valves or recharge unit. Check refrigerant

charge.

Step 4—Install Solenoid Valve In Liquid Tube (If Re-
quired)

Not all applications require use of a liquid tube solenoid
valve. If your unit has been shipped with a liquid tube
solenoid valve in the unit, it must be installed for performance
enhancement. The liquid tube solenoid valve must be ener-
gized during evacuation for complete removal of refrigerant.

Before making liquid tube connections, install factory-supplied
solenoid valve on indoor liquid fitting. (See Fig. 6.) Be sure to use
flare adapter supplied with the indoor coil when making connec-
tions.

Wiring must comply with local codes and NEC requirements,
if a field-supplied control power source is needed when
adding solenoid.

1. Remove coil liquid connection cap and discard.

2. Mount solenoid valve on liquid tube, making sure valve flow

arrow points toward indoor coil. Mount valve in any position
except valve body at top and electric coil at bottom. (See Fig.

Fig. 2—Refrigerant Tube Dimensions/Connections

UNIT SIZE

LIQUID TUBE

VAPOR TUBE

Conn Dia

Tube Dia

Conn Dia

Tube Dia

018, 024

3/8

3/8

5/8

5/8

030, 036

3/8

3/8

3/4

3/4

042, 048

3/8

3/8

7/8

7/8

060

3/8

3/8

7/8

1-1/8

Tube diameters are for lengths up to 50 ft. For tubing lengths greater than 50
ft, consult your local distributor.

A93578

LIQUID LINE CONN

FIELD CONTROL 
SUPPLY CONN

7

8

″ 

DIA HOLE

FIELD POWER 
SUPPLY CONN

7

8

″ 

DIA HOLE WITH 

1

8

″ 

DIA KNOCKOUT

AND 1 

3

8

″ 

DIA

KNOCKOUT

AIR DISCHARGE

SUCTION LINE CONN

Fig. 3—Mechanical Fitting Assembly (38CKN)

A92120

VALVE FITTING

FERRULE

LOCK NUT

Fig. 4—Lock Nut/Ferrule Positioning (38CKN)

A92121

FERRULE

LOCK NUT

TUBING

Fig. 5—Proper Marking of Valve Assembly (38CKN)

A92122

LOCK NUT

MARK ON LOCK NUT 
AND TUBE

TUBING