13 - AQUASNAP MAINTENANCE PROGRAM

All maintenance operations must be carried out by technicians
who have been trained on Carrier products, observing all
Carrier quality and safety standards.

Maintenance instructions
During the unit operating life the service checks and tests must
be carried out in accordance with applicable national regulations.

If there are no similar criteria in local regulations, the
information on checks during operation in annex C of standard
EN 378-2 can be used.

External visual checks: annex A and B of standard EN 378-2

Corrosion checks: annex D of standard EN 378-2. These
controls must be carried out:
-

After an intervention that is likely to affect the resistance
or a change in use or change of high-pressure refrigerant,
or after a shut down of more than two years. Components
that do not comply, must be changed. Test pressures
above the respective component design pressure must not
be applied (annex B and D).

-

After repair or significant modifications or significant
system or component extension (annex B)

-

After re-installation at another site (annexes A, B and D)

-

After repair following a refrigerant leak (annex D). The
frequency of refrigerant leak detection can vary from once
per year for systems with less than 1% leak rate per year
to once a day for systems with a leak rate of 35% per year
or more. The frequency is in proportion with the leak rate.

NOTE: High leak rates are not acceptable. The necessary
steps must be taken to eliminate any leak detected.

NOTE 2: Fixed refrigerant detectors are not leak detectors,
as they cannot locate the leak.

13.1 - Maintenance schedule

Regular maintenance is indispensable to optimise the operating
life and reliability of the equipment. Maintenance operations
must be carried out in accordance with the schedules below:

Service

Frequency

A

Weekly

B

Monthly

C

Annually

D

Special cases

If the equipment does not operate normally during maintenance
operations, please refer to the paragraph on diagnostics and
breakdowns of the '30RA/RH- 30RY/RYH “B” Pro-Dialog Plus'
controls manual.

IMPORTANT: Before each equipment maintenance
operation please ensure that:
-

the unit is in the OFF position

-

it is impossible for the unit to restart automatically
during maintenance.

13.2 - Description of the maintenance operations

The equipment is supplied with polyolester oil (POE). Only
use oil approved by Carrier. On request Carrier can carry out
an oil analysis of your installation.

Service A
Full-load operating test
Verify the following values:
-

compressor high-pressure side discharge pressure

-

compressor low-pressure side suction pressure

-

charge visible in the sight glass

-

temperature difference between the heat exchanger water
entering and leaving temperature.

Verify the alarm status

Service B
Carrier out the operations listed under Service A.
Refrigerant circuit
-

Verify the air heat exchanger cleanliness status and clean
it at least once a year, or more often if the equipment
environment is especially demanding. To clean the
equipment, follow the Carrier recommendations. Among
other things, this ensures that the unit performances can
be guaranteed.

-

Full-load operating test. In addition to the operations
described under Service A, check the following values:
-

compressor discharge pressure

-

compressor oil level

-

actual liquid subcooling

-

overheating at the expansion device

-

on heat pumps verify correct defrost of the air heat
exchanger.

-

Verify the charge status by checking the colour indicator
of the sight glass. If the colour has turned to yellow,
change the charge and replace the filter drier after
carrying out a leak test of the circuit.

Electrical checks
-

Check the tightening of the electric connections,
contactors, disconnect switch and transformer.

-

Check the status of the contactors, fuses and capacitators,
as required.

-

Carry out a quick test (refer to the manual for the
Aquasnap Pro-Dialog Plus control).

Mechanical checks
-

Verify that nothing impedes the rotation of the fan
impeller of the air heat exchanger.

Water circuit checks
-

Check the leak-tightness of the circuit.

Summary of Contents for 30RY 017

Page 1: ...Installation operation and maintenance instructions AQUASNAP For the operation of the control please refer to the Pro Dialog Control manual for the 30RA RH 30RY RYH B series Carrier is participating...

Page 2: ...loop volume 12 6 6 30RY unit operating range at full and part load 12 6 7 Pressure drop in the plate heat exchangers 13 7 ELECTRICAL CONNECTION 14 7 1 Power supply 15 7 2 Voltage phase imbalance 15 8...

Page 3: ...tual subcooling 24 12 4 Refrigerant guidelines 25 12 5 Recharging liquid refrigerant 25 12 6 Undercharge 25 12 7 Characteristics of R407C 25 12 8 Electrical maintenance 25 12 9 Condenser coil 26 13 AQ...

Page 4: ...d before operating the unit In certain cases the globe stops are installed on ball valves These valves are factory supplied lead sealed in the open position This system permits isolating and removing...

Page 5: ...ioration and injuries to people Faults and leaks must be repaired immediately The authorized technician must have the responsibility to repair the fault immediately Each time repairs have been carried...

Page 6: ...be trapped between this valve and the expansion device This valve is situated on the liquid line before the filter drier box Do not attempt to repair or recondition any safety devices when corrosion o...

Page 7: ...connections and service operations For the centre of gravity coordinates the position of the unit mounting holes and the weight distribu tion points refer to the certified dimensional drawing supplied...

Page 8: ...s and arrangements are in place and comply with the current European standard Verify that all document for pressure containers certificates name plates files instruction manuals that are required docu...

Page 9: ...location of fixing points weight distribution and coordinates of the centre of gravity refer to the certified dimensional drawings B Install a condensate collection channel around the unit or install...

Page 10: ...070 080 Power circuit Nominal power supply V ph Hz 400 3 50 Voltage range V 360 440 Control circuit supply The control circuit is supplied via the unit mounted transformer Maximum unit power input kW...

Page 11: ...re range 10 C to 46 C class 4K3 altitude 2000 m presence of hard solids class 4S2 no significant dust present presence of corrosive and polluting substances class 4C2 negligible vibration and shock cl...

Page 12: ...vaporator T of 2 8 K must be guaranteed which corresponds to a water flow rate of 0 9 l s per kW 6 5 Water loop volume 6 5 1 Minimum water loop volume The minimum water loop volume in litres is given...

Page 13: ...17 2 30RY 021 3 30RY 026 4 30RY 033 5 30RY 040 6 30RY 050 7 30RY 060 8 30RY 070 9 30RY 080 1 10 100 1000 2000 1 10 1 2 3 4 5 6 7 8 9 6 7 Pressure drop in the plate heat exchangers Pressure drop kPa Wa...

Page 14: ...ections For copper cables use electrolytic copper AMP type cable stiffeners with 6 mm terminal for sizes 017 to 080 30RY X mm Y mm 017 033 1180 761 040 080 190 762 NOTES The 30RY units have only one p...

Page 15: ...isolator switch are designed for the number and type of wires listed in the table below The calculations are based on the maximum machine current see electrical data tables and the standard installati...

Page 16: ...be recommended 10 pH Ideal case pH neutral at 20 25 C 7 pH 8 ATTENTION Charging adding or draining fluid from the water circuit must be done by qualified personnel using air vents and materials suitab...

Page 17: ...n switching the unit off in winter Add ethylene glycol with an adequate concentration to protect the installation up to a temperature of 10 K below the lowest temperature likely to occur at the instal...

Page 18: ...c module are equipped with a flow switch and an internal piping heater Legend Components of the unit and hydronic module 1 Victaulic screen filter 2 Expansion tank 3 Safety valve 4 Available pressure...

Page 19: ...rve to obtain the desired operating point see example for 30RY 080 The pres sure drop reading in the plate heat exchanger is used to control and adjust the nominal system flow rate The pressure drop i...

Page 20: ...ly closing the control valve until you obtain the specific pressure drop that corresponds to the nominal flow rate at the required unit operating point If the system has an excessive pressure drop in...

Page 21: ...ide a removable window on the return air duct to permit maintenance of the air temperature sensor 10 5 2 Air return with accessory filter The suction side connection collar must first be removed Insta...

Page 22: ...ry Filter access for maintenance is ensured by removing the two Metric screws on the unit side rear view of the unit The cover panel supplied with a handle can now be removed The filters are attached...

Page 23: ...ntactor power supply If the pump is not supplied with the unit unit without hydronic module verify that the power input of the field installed pump does not exceed the rating of the standard pump cont...

Page 24: ...heck all heat exchangers and all pipework If water jets are used inside the units e g to clean the coils the lower holes for possible condensate removal must be blocked 12 2 Verification of the refrig...

Page 25: ...specialists Their activities must be overseen and checked by properly trained people To minimise discharge to the atmosphere refrigerants and lubricating oil must be transferred using methods which re...

Page 26: ...4 51 04 28 75 63 67 67 64 10 22 12 27 77 19 5 46 77 51 55 29 64 07 68 02 10 25 22 94 28 56 19 75 47 29 52 05 29 25 64 47 68 39 12 9 Condenser coil We recommend that finned coils are inspected regularl...

Page 27: ...operations please refer to the paragraph on diagnostics and breakdowns of the 30RA RH 30RY RYH B Pro Dialog Plus controls manual IMPORTANT Before each equipment maintenance operation please ensure tha...

Page 28: ...ssors fans and pumps Check the compressor fan and pump winding status Mechanical checks Check the tightening of the fan tower fan compressor and control box fixing bolts Check that no water has penetr...

Page 29: ...mage prevent unit start up Unit is level in its installation Power supply agrees with the unit name plate Electrical circuit wiring has been sized and installed properly Unit ground wire has been conn...

Page 30: ...to 080 3 50 litres nominal kW capacity for air conditioning 30RY 017 to 040 Proper loop volume established Proper loop corrosion inhibitor included litres of Proper loop freeze protection included if...

Page 31: ...this machine Once all checks have been made start the unit in the LOCAL ON position Unit starts and operates properly Temperatures and pressures WARNING Once the machine has been operating for a while...

Page 32: ...persedes order No 13427 76 04 2002 Manufactured by Carrier SA Montluel France Manufacturer reserves the right to change any product specifications without notice Printed in the Netherlands Printed on...

Reviews: