Maintenance And Service

The air conditioning unit is an equipment and users are suggested to record the daily operation data of the equipment and to 
conduct regular maintenance and service.
1. The following inspections shall be conducted properly before the use of the equipment:

♦  Shall be inspected to ensure that the wiring is correct and that there are no abnormalities on the rotation of the fan as per 

the operation and maintenance manual

♦  Shall be conducted to ensure that all the power supply lines and control lines are connected correctly, and that the 

wiring adheres to the given wiring diagram. Reliability checks on grounding have to be conducted, and all the connection 

terminals are to be checked and confirmed secured.

♦  The inspection shall be conducted to confirm whether all power supply lines and control lines are connected in position 

and whether the wiring is correct according to the wiring diagram, whether the grounding is reliable and whether all 
connection terminals are secure.

2. Daily maintenance during the equipment use:

3. We recommend the following maintenance and service methods for the equipment which is not used for a long time

♦  In case that the unit does not operate for a long time or does not operate in winter, the power must be turned off and the 

water shall be discharged from the water system and the steam coil of the unit.

♦  If necessary, the maintenance and service may be conducted according to the pre-use maintenance and service methods 

of the equipment.

       Note

1. User service: mandatory inspection -    recommended inspection - 

2. Vulnerable parts required for the service shall be purchased from CARRIER.

3. The service methods apply to the cycle during normal use and the arrangement shall be made based on actual conditions in case of use in bad conditions.

Unit maintenance contents

Standard service cycle

Remarks

Monthly Quarterly

Half-yearly

1. The inspection shall be inspected to confirm 

whether the power line (from the distribution cabinet 

to the unit) is loose or damaged.

2. The inspection shall be conducted to confirm 

whether the condensate discharge is normal.

Is the installation conducted according to the pipe connection 

diagram? Is it dirty or blocked? Is the drainage smooth? Is there 

any overflow, etc. due to this?

3. The inspection shall be conducted to confirm 

whether there is abnormal noise during the operation 

of the unit.

For instance, sharp metal friction sound, whistlers, obvious clash 

or resonance, significant electromagnetic noise (disgusting) and 

other abnormal noise.

4. The inspection shall be conducted to confirm

whether it is necessary to clean the air side of heat

exchanger (surface dust, sundries, etc.)

Spaces among fins are full of dust and there are sundries 

attached on the inlet side of the coil, etc.

5. The inspection shall be conducted to confirm

whether the air strainer is dirty or blocked and whether

it is necessary to clean or replace the strainer.

The differential pressure alarm value and the scale value in the 

differential pressure gauge reach the  

final resistance value, etc.

AIR HANDLING UNIT

21

CARRIER

Summary of Contents for 010

Page 1: ...AC Fan Mini Air Handling Unit Ceiling Concealed Type ...

Page 2: ...on fire security and building automation technologies Supported by the iconic Carrier name the company s portfolio includes industry leading brands such as Carrier Kidde Edwards LenelS2 and Automated Logic Carrier s businesses enable modern life delivering efficiency safety security comfort productivity and sustainability across a wide range of residential commercial and industrial applications ...

Page 3: ...antages 4 Features 6 Nomenclature 7 General Data 8 Jet Type Unit Design Selection 13 Dimension 14 Wiring Diagrams 17 Installation 18 Precautions For Installation And Use 19 Maintenance And Service 21 AIR HANDLING UNIT 3 CARRIER ...

Page 4: ...rough the advanced mechanical expansion tube process The coil passes air tightness test before delivery to ensure no leakage The cabinet interior is isolated from the exterior via polyurethane foamed under high pressure and specially designed rubber sealing strip to avoid cold bridge Cold bridge factor can reach AHRI1350 CB2 The external metal plate of the cabinet is surrounded by the aluminum fra...

Page 5: ... thermal insulation effects but also reduces the unit operation noise Mechanical electrical integration control enables integrated control of fan motor and water valve The control system is composed of low voltage apparatuses and temperature controllers from internationally well known brands If the unit is equipped with a temperature controller with communication function the unit can access third...

Page 6: ...dge Frames of aluminum sections are embedded around all panels completely isolating corners of metal panel from air and moisture and thereby preventing rust spot on panels No water leakage The unit adopts the one piece drain pan which is covered by seamlessly integrated insulation materials after overall coating by spraying equipment of advanced German technology The drain pan installed on the uni...

Page 7: ...l N No cooling coil R Return air F Fresh air L Left face supply air R Right face supply air C Ceiling type F Product generation 030 Air flow 3000CMH TF Ceiling Type Standard Air Handling Unit The unit is left type Air flow Air flow Facing the air flow if the water piping is on the left this is a left type unit and Facing the air flow if the water piping is on the right this is a right type unit Me...

Page 8: ...e 39TF m3 h kW kW I s kPa kW DN kW kW I s kPa kW DN Pa dB A DN 380V 3N 50Hz Direct Drive 010 1000 5 1 10 2 0 24 3 0 0 18 32 7 2 12 4 0 34 8 8 0 18 32 80 53 25 015 1500 8 3 15 2 0 40 9 0 0 32 32 11 0 18 5 0 52 19 5 0 32 32 80 53 25 020 2000 11 5 21 2 0 55 11 0 0 32 32 14 9 25 3 0 71 26 0 0 32 32 80 55 25 025 2500 14 4 26 0 0 69 18 0 0 55 32 18 2 30 8 0 87 38 0 0 55 32 120 56 25 030 3000 17 5 32 0 0...

Page 9: ...0 17 0 2 2 50 105 6 104 8 5 03 80 0 2 2 65 240 64 25 080 8000 99 0 101 7 4 71 14 4 2 2 50 120 7 119 7 5 75 30 0 3 0 65 240 64 25 090 9000 111 0 113 8 5 29 19 0 3 0 65 137 3 135 3 6 54 41 0 3 0 65 280 66 25 105 10500 133 1 133 3 6 34 31 0 3 0 65 160 2 157 9 7 63 57 9 4 0 80 280 67 25 120 12000 149 4 155 1 7 12 35 0 4 0 65 185 2 180 4 8 20 68 8 4 0 80 280 68 25 135 13500 165 8 180 2 7 90 33 0 4 0 80...

Page 10: ... 5 2 2 2 2 6 1 5 1 5 1 5 1 5 2 2 2 2 2 2 060 6000 4 1 5 1 5 1 5 1 5 2 2 2 2 2 2 6 1 5 1 5 1 5 2 2 2 2 2 2 2 2 070 7000 4 1 5 1 5 2 2 2 2 2 2 2 2 2 2 6 1 5 2 2 2 2 2 2 2 2 2 2 3 0 080 8000 4 2 2 2 2 2 2 2 2 2 2 3 0 3 0 6 2 2 2 2 2 2 2 2 3 0 3 0 3 0 090 9000 4 2 2 2 2 2 2 2 2 2 2 3 0 3 0 6 2 2 2 2 2 2 2 2 3 0 3 0 3 0 105 10500 4 3 0 3 0 3 0 3 0 3 0 3 0 4 0 6 3 0 3 0 3 0 3 0 3 0 4 0 4 0 120 12000 4 3...

Page 11: ...07 63 0 1 5 50 75 4 70 3 3 59 51 0 2 2 50 25 060 6000 72 7 75 5 3 46 74 0 1 5 50 92 6 91 9 4 41 57 0 2 2 50 25 070 7000 84 1 87 1 4 00 17 0 1 5 50 105 6 104 8 5 03 80 0 2 2 65 25 080 8000 99 0 101 7 4 71 14 4 2 2 50 120 7 119 7 5 75 30 0 3 0 65 25 090 9000 111 0 113 8 5 29 19 0 2 2 65 137 3 135 3 6 54 41 0 3 0 65 25 105 10500 133 1 133 4 6 34 31 0 3 0 65 160 2 157 9 7 63 57 9 3 0 80 25 120 12000 1...

Page 12: ...ecifications without prior notice 3 Pressure drop of heating coil is 20Pa per row NOTE 1 Heating capacity is based on the following a Inlet and outlet water temperature 60 C 50 C b Air entering condition 7 C DB 2 The manufacturer reserves the rights to make changes to the above specifications without prior notice 3 Pressure drop of heating coil is 20Pa per row Model Air Flow 1Row 2Row Rated Heatin...

Page 13: ...cold and hot air flow supplied by the unit must meet the following requirements 1 The cold and hot air are sent to the specified location 2 The cold jet flow does not drop down during the supply process to avoid causing discomfort to people 3 The hot air can be sent to the required distance and location 4 Temperature difference meets the design requirement Design selection must take into account t...

Page 14: ...57 015 867 545 900 703 505 800 302 275 643 445 302 275 57 63 020 927 620 900 763 580 800 302 275 703 520 302 275 71 81 025 1017 620 900 853 580 800 302 306 793 520 302 306 76 86 NOTE 1 If add heating coil F need to plus 100mm 2 The above weight and size do not include the built in control cabinet Chilled water outlet pipe Chilled water inlet pipe Lifting hole φ 14mm Junction box Condensate water p...

Page 15: ...09 244 341 1973 670 862 341 279 309 120 2298 840 1050 2134 790 950 395 324 341 2074 730 1114 341 287 311 135 2248 940 1150 2084 890 1050 373 294 404 2024 730 1040 404 368 398 150 2218 1040 1150 2054 990 1050 373 294 404 1994 930 1040 404 372 414 NOTE 1 The value 25 20 is the distance between the lifting hole and the outer edge of the unit base It is 20 for 040 type and smaller type and is 25 for t...

Page 16: ...0 1450 2 315 384 190 188 196 040 1357 620 1590 1193 580 1450 2 400 467 230 201 210 050 1547 630 1590 1383 580 1450 2 400 467 230 228 239 060 1652 690 1600 1488 640 1450 2 500 600 275 249 262 070 1842 690 1600 1678 640 1450 2 500 600 275 292 307 080 1772 780 1600 1608 730 1450 2 500 600 275 343 358 090 1947 780 1690 1783 730 1550 3 400 467 230 376 393 105 2197 780 1700 2033 730 1550 3 500 600 275 3...

Page 17: ...39TF D B S Wiring Diagrams AIR HANDLING UNIT 17 CARRIER ...

Page 18: ... and a fire damper in accordance with fire control requirements If an electric air volume control valve is installed start the air valve actuator and then the fan while close the fan and then the air valve actuator U Type Water Seal Installation Ball Type Water Seal Installation Wash the water pipes before connecting them Pay attention to the cold hot water inflow and outflow directions connect th...

Page 19: ...ly at the interval of 1 2 months its good heat transfer effect can be maintained and the energy can be saved The drain pipe must be laid according to the requirements in the Instruction to ensure smooth water drainage and proper measures for thermal insulation shall be taken to prevent the generation of condensate The drain pipe must be inspected before the unit operates In case of blockage foreig...

Page 20: ...ucted every three months of operation in future The wiring pile head of the wire will be loosened after the unit operates for a certain time It shall be inspected and tightened on the third day upon the first startup Bearings for the fan and the motor shall be inspected regularly three times per month as recommended The seal ring of the motor bearing for instance V seal ring shall be inspected and...

Page 21: ...he pre use maintenance and service methods of the equipment Note 1 User service mandatory inspection recommended inspection 2 Vulnerable parts required for the service shall be purchased from CARRIER 3 The service methods apply to the cycle during normal use and the arrangement shall be made based on actual conditions in case of use in bad conditions Unit maintenance contents Standard service cycl...

Page 22: ...Note 22 CARRIER ...

Page 23: ...Note AIR HANDLING UNIT 23 CARRIER ...

Page 24: ...The Manufacturer reserves the right to change any produt specifications without prior notices ...

Reviews: