FT-145 Williamsburg Pineapple 2-Tier in Basin Fountain
Professional installation is recommended for this fountain!
Assemble your fountain on a level surface using crushed stone, gravel, or cement pad as the base.
Revised March 31, 2017
FGB-2030 (130 lbs)
72”W x 11.75”H
FT-145F (50 lbs)
15.5”W x 9”H
FT-145E (90 lbs)
14.75”W x 22.75”H
FT-145D (111 lbs)
30”W x 8.5”H
FT-145C (18 lbs)
7”W x 15.25”H
1.
Place the fiberglass basin where the fountain is to be installed.
a.
Be sure to check that each part is level and centered during the
assembly of this fountain.
2.
Spread a thin amount of silicone on both pump cords approximately 3 feet
from the pumps and fit them into the double holed stopper.
3.
Feed the pump cords through the hole in the basin.
4.
To ensure a level installation, make sure that you run the remaining cord
through the channel in the bottom of the basin.
5.
Press stopper firmly and evenly into the hole of basin.
6.
Spread a thin bead of silicone around the perimeter of the stopper, slit in
the stopper, and around the pump cords.
7.
Loosely wrap cords up in the center of the basin.
8.
Place the fountain base (FT-145F) over the pumps and the cords.
9.
Place the large pedestal (FT-145E) on top of the base.
10.
Position the large bowl (FT-145D) on top of the large pedestal (FT-145E).
11.
Connect the 1/2" non-kink side of the 36” preassembled tubing to the pipe
protruding from the bottom of the large bowl (FT-145D).
12.
Feed the clear vinyl tubing through the hole in the large pedestal (FT-
145E).
13.
Fit the tubing to the pump water outlet on the pump.
14.
Using a hose clamp, secure the 16” length of non-kink tubing to the pipe
protruding inside the large bowl (FT-145D).
15.
Feed the non-kink tubing through the small pedestal (FT-145C).
16.
Center the small pedestal (FT-145C) inside the large bowl (FT-145D).
FT-132B (20 lbs)
16.5”W x 4.5”H
FT-132A (3 lbs)
3.75”W x 7”H
FT-145G (8 lbs)
5.5”L x 2”W x 5”H
FT-145H (228 lbs each)
40.25”L x 9”W x 15.25”H
17.
Using a hose clamp, connect the loose end of the non-kink tubing to the
pipe protruding from the bottom of the small bowl (FT-145B).
18.
Center the small bowl (FT-145B) on the small pedestal (FT-145C)
19.
Place the finial (FT-132A) into the small bowl (FT-132B) by fitting the
copper in the finial over the copper in the bowl.
20.
Fit the pump cover door (FT-145G) into the pump cover (FT-145F).
21.
Position the copings (FT-145H) in a circle about 6 inches from the basin.
22.
Carefully push each piece one at time toward the basin and into the notch
of the coping.
a.
Fit each piece to the coping next to it.
23.
Fill the basin with water.