 8     AIM-50™ Installation Manual 

 Double Ceiling Version 5000147 A01   

Double Ceiling Version Installation 

Ceiling Support Structure 

The engineer of record for the building shall provide a support structure designed to support 
weights and forces shown on the Equipment Anchorage Diagrams on page 19. When the support 
structure is in place the static inspection sheet on page 18 should be filled out and stored for future 
reference

.  

Installing the Junction Box 

The junction box should normally be placed on top of the support structure. Make sure the screw 
holes on the junction box plate correspond to the holes in the ceiling casting. When the ceiling 
plate is installed, the bolts will also hold the junction box.  
 
If there isn’t space for the junction box on top of the support structure, another suitable location in 
the ceiling can be used. It is also possible to use a different junction box if that is more convenient.  
 
See wiring diagram on page 11: 
Switch wiring (contractor-supplied) must be minimum AWG 18 from the switch to the terminal 
block. Wiring and conduit must meet the NEC, local, and national fire protection codes. 

 
Installing the Ceiling Casting 

 

Note: Illustration is for single ceiling version, so only one transformer and a smaller terminal block is shown.  

 
1.

 

The static inspection sheet on page 18 has to be filled out and signed by a certified engineer or 
Construction Authority before mounting the ceiling casting. 

   

Summary of Contents for AIM-50

Page 1: ...INSTALLATION MANUAL DOUBLE CEILING VERSION PERFORMANCE RELIABILITY VALUE AIM 50 The Right Light EXAMINATION...

Page 2: ......

Page 3: ...ing Version 100 V A52 DC AIM 50 Double Ceiling Version 240 V A53 DC AIM 50 Double Ceiling Version 230 V This product was designed and assembled in the U S A by BURTON MEDICAL PRODUCTS CORP 21100 Lasse...

Page 4: ...talling the Ceiling Casting 8 Installing the Down Tube 9 Connecting Power 11 Installing Wall Switch 13 Installing the Extender Arms with Spring Arm 14 Mounting the Light Heads 15 Final Testing 17 Adju...

Page 5: ...nance and further description of the product please refer to the Operation Maintenance manual furnished with the product Please read these installation instructions very carefully and follow the safet...

Page 6: ...roperly follow installation and preventive maintenance instructions may result in mechanical failure WARNING Before undertaking any work ensure that the branch circuit power is off and secured from ac...

Page 7: ...roper height of the light should be set by the end user This depends on the ceiling height the height of the examination tables types of procedures and the user s preferences See Figure 1 on page 6 Du...

Page 8: ...6 AIM 50 Installation Manual Double Ceiling Version 5000147 A01 Range of Motion Figure 1 Range of motion shown for 9 ft ceiling and 16 inch down tube...

Page 9: ...nside containers and examine all packing material to ensure small articles are not overlooked If a Shortage or Damage Occurs 1 You the receiver not Burton are responsible for filing any claim s with t...

Page 10: ...he ceiling casting When the ceiling plate is installed the bolts will also hold the junction box If there isn t space for the junction box on top of the support structure another suitable location in...

Page 11: ...in a triangular pattern See Equipment Anchorage Diagrams on page 19 for details Installing the Down Tube NOTE The down tube is pre cut and pre drilled at the factory and will suite most exam rooms wi...

Page 12: ...set screw which is a dog point screw Make sure it fully engages the matching hole in the down tube Then fasten the lower setscrew Use Loctite Threadlocker or similar adhesive on the screws to prevent...

Page 13: ...ws the view looking up toward the ceiling casting Only installation connections are shown For a complete wiring diagram please refer to the Operation Maintenance manual The switches are shown out of p...

Page 14: ...stallation Manual Double Ceiling Version 5000147 A01 3 Push the bell housing and the lock ring up until it covers the ceiling casting Tighten the two set screws on the lock ring using an Allen key 3 3...

Page 15: ...ished with the product to a standard junction box per local codes The wires that go to the light fixture are labeled to light fixture 100V 230V 240V versions Install the wall switch per local codes Wa...

Page 16: ...Unscrew the cross slotted Phillips screw a 2 Remove the plug cap b from one arm 3 Slide the arm onto the shaft of the double transition d 4 Place the washer c on the shaft and install the retaining r...

Page 17: ...st be properly installed to avoid safety hazard Figure 1 Figure 2 1 Figure 1 above shows the correct orientation of the spring arm to the light head 2 Loosen the brake screw b and remove the protectiv...

Page 18: ...e groove h See figure 4 Figure 5 8 Rotate the collar c 180 degrees as shown in figure 5 9 Before installing the brake screw b check the attachment of the light head by pulling and rotating it at the s...

Page 19: ...inside the arm is pre adjusted at the factory If however the light head drifts up or down please refer to the Operation Maintenance manual for guidance on how to adjust it Cutting the Down Tube If sho...

Page 20: ...the structural engineer who is responsible for the installation must be contacted since adequate static load distribution in the ceiling may have been jeopardized Declaration of Acceptance I hereby c...

Page 21: ...AIM 50 Installation Manual Double Ceiling Version 5000147 A01 19 Equipment Anchorage Diagrams Double Ceiling Version Overview...

Page 22: ...20 AIM 50 Installation Manual Double Ceiling Version 5000147 A01 Double Ceiling Version Plan Ceiling...

Page 23: ......

Page 24: ...BURTON MEDICAL 21100 Lassen Street Chatsworth CA 91311 USA Phone 800 444 9909 818 701 8700 Fax 800 765 1770 818 701 8725 www burtonmedical com The Right Light...

Reviews: