22
TFS/OFS-33 ONLY:
After the
second row
of firebox is
complete, install Smoke Shelf and remaining side walls
(Figure 31). Mix approx. 2
cu. ft.
of Ready-Mix Concrete.
Insert 28” rebar vertically through the cells, into the holes
in the hearth, adjacent to the rebar and/or all-thread
sticking up from the hearth. Fill all cells with Ready-Mix
Concrete mix.
Figure 31
Install rebar adjacent
to all-thread or rebar
stemming from floor.
TFS/OFS-33
Only
Install Smoke Shelf TFS33-4
after 2nd row of walls.
Add rebar and fill all
cells with concrete mix
Set the Lintel and Lower Rear Dome in place as shown
in
Figures 32
. Check that all is level. If you need to make
adjustments, use shims. Place one or more of these
shims between the lowest wall component and the top
surface of the base plate. Once you are satisfied with
the degree of levelness, you can address any gap that
may have occurred with an appropriate amount of mortar.
Note:
Although you are cautioned to use Burntech® mortar
sparingly because it does have such holding power, you
should look over the firebox assembly at the end and fill
in any gaps, especially joint connections, with the mortar.
Important:
Adjustments can only be made while the mortar
is still wet when correcting for squareness and leveling.
Assemble Lower Dome Sides as shown in
Figure 32
. The
beveled face lines up with the inward angles of the lintel
sides. Top surfaces should be level.
Lower Rear Dome
TFS/OFS
33-5
Lintel Front
Lower Dome
Sides
TFS/OFS
33-7
These
surfaces
should
be flush.
T-Bar
Figure 32
Apply mortar
to all adjoining
surfaces
8.
9.
10.
As you are connecting each Burntech® component, be
certain you are following the instructions given previously
for using Burntech® mortar. Stop to look at the smoke
dome side, front and rear walls to see that they are aligning
correctly and that the surfaces are smooth and uniform.
Make sure connections are covered with an adequate
amount of mortar. Remember that you have the option
of using shims but they must be removed and any holes
filled. Make any adjustments to the fireplace alignment
before continuing to the next step.
Assemble Upper Dome (
TFS/OFS
33-10) and Dome Sides
(
TFS/OFS
33-8) as shown in
Figure 33
. Check your assembly
here. If things are proceeding as they should be, the
finished top surface should be flat and level.
Finally, set the Dome Top into position. Be sure that it is
flush in every direction as you place it on the crest of the
smoke dome wall assembly. After this is done, proceed to
section on “Installing Damper and Chimney System” on
page 26.
Note:
The chimney hole on the Dome Top is not centered
from front to back - it should be offset closest to the rear of the
fireplace (see
Figure 33
).
11.
12.
13.
TFS/OFS-33 Fireplace Assembly
Dome Sides
TFS/OFS
33-8
Upper Domes
TFS/OFS
33-10
Figure 33
Dome Top (TFS/OFS 33-9)
Center of chimney hole is offset towards the rear.
Position marker towards front as shown.
TFS/OFS-33
Summary of Contents for OFS-33
Page 2: ...This page has been left intentionally blank ...
Page 39: ......