12

Install  Downdraft  Diverter  and  final  row  of  Side  Walls 

(

Figure  17

). Then  place  #3  rebar  (8  each,  36  inch  long) 

vertically through the cells until they reach bottom. Position 

them adjacent to the rebar or all-thread sticking up from the 

hearth.
All components must be level. Mix approx. 2 cu. ft. of Ready-

Mix  Concrete.  Fill  all  cells  with  Ready-Mix  Concrete  mix.

 

Figure 17

Downdraft 

Diverter 

12 inch

rebar or 

all-thread

Set the Lintel and Lower Rear Dome as shown in 

Figure 

19

. Check that all is level. If adjustments are needed, use

shims and fill gaps with an appropriate amount of mortar.

 

Note: 

Although you are cautioned to use Burntech® mortar 

sparingly  because  it  does  have  such  holding  power,  you 

should look over the firebox assembly at the end and fill in 

any  gaps,  especially  joint  connections,  with  the  mortar. 

 

Figure 19

Lintel

Lower Rear 

Dome

Important:

 Adjustments can only be made while the mortar 

is still wet when correcting for squareness and leveling.

8.

9.

10.

Assemble Lower Dome Sides as shown in 

Figure 20

. The 

beveled face lines up with the inward angles of the lintel 

sides. Resulting top surfaces should be level. 

Figure 20

Lower Dome Sides (Rating 

Plate faces inside)

Verify that the smoke dome side, front and rear walls are 

aligning  correctly  and  that  the  surfaces  are  smooth  and 

uniform.    Make  sure  connections  are  covered  with  an 

adequate amount of mortar. Remember that you have the 

option of using shims but they must be removed and any 

holes filled. Make any adjustments to the fireplace alignment 

before continuing to the next step.

Assemble  Upper  Dome  and  Dome  Sides    as  shown  in 

Figure  21

.  Check  your  assembly  here.  If  things  are 

proceeding  as  they  should  be,  the  finished  top  surface 

should be flat and level. 

Figure 21

Upper Dome Sides

Upper Dome

Front/Rear

Finally, set the Dome Top into position. Be sure that it is 

flush in every direction as you place it on the crest of the 

smoke dome wall assembly. After this is done, proceed to  

section on “Installing Damper and Chimney System”

.

Note: 

The chimney  hole on the Dome Top is not centered from 

front  to  back  -  it  should  be  offset  closest  to  the  rear  of  the 

fireplace (see 

Figure 22). 

Figure 22

C

enter of chimney hole 

is 

offset towards the rear.

10”

12-1/2”

GBVS-39/44/49

11.

12.

13.

14.

Summary of Contents for GBVS 39/44/49

Page 1: ...0 standard Solid fuels shall not be burned in this fireplace This appliance must be vented vertically through the roof This appliance is not for installation in manufactured or mobile homes The instal...

Page 2: ...THIS PAGE INTENTIONALLY LEFT BLANK...

Page 3: ...YPE DO NOT REMOVE THIS LABEL See Burntech Installation Operating Instructions for this model Contact local building officials about restrictions and installation specifications in your area THIS FIREP...

Page 4: ...ponents Warning Failure to position the parts in accordance with these diagrams or failure to use only parts specifically approved with this appliance may result in property damage or personal injury...

Page 5: ...DESCRIPTION QTY 1 TFS39 1 TFS44 1 TFS49 1 HEARTH Left or Right 2 2 TFS39 2 TFS44 2 TFS49 2 REAR WALL 3 3 TFS39 3 TFS44 3 TFS49 3 SIDE WALL 7 3A TFS39 3A TFS44 3A TFS49 3A SIDE WALL with 4 opening for...

Page 6: ...ent parts and accessories as listed in these parts lists Before beginning installation be sure the burner system is complete by comparing its contents with this Parts List Parts may differ depending u...

Page 7: ...illustrations in this manual are for general reference only Do not scale drawings Actual design elements will vary from case to case Pay attention to specified minimum clearances to combustibles WARNI...

Page 8: ...accessories Use of other controls parts and accessories which are not designed for use with Burntech gas fireplaces is prohibited and will void all warranties certifications listings and building code...

Page 9: ...t reading these procedures will save you time and at the most it will prevent any malfunction that could result in property damage or serious injury Do not start the installation until you have checke...

Page 10: ...he addition of floor joists to align with the anchor brackets allows the brackets to be directly connected to the floor joists Note that additional floor joists may be required to support the weight o...

Page 11: ...at time of installation and used under dry conditions the deflection resulting from L 0 5D is permitted to be substituted for the deflection resulting from L D Note that Burntech cannot accept respons...

Page 12: ...washers GBVS 44 49 Eight 8 pieces 3 8 rebar x 36 long included with unit Eight 8 ea All thread x 12 long with nuts and washers ALL UNITS Three 3 90 lb bags of ready mix concrete with 1 4 or smaller ag...

Page 13: ...latness level if necessary Figure 13 1 2 away from edges 1 2 mortar bead typical Hearth section shown prepared for Right Side position Apply mortar bead to all mating surfaces Apply mortar to the rema...

Page 14: ...veled face lines up with the inward angles of the lintel sides Resulting top surfaces should be level Figure 20 Lower Dome Sides Rating Plate faces inside Verify that the smoke dome side front and rea...

Page 15: ...5 Fireplace Finishes Combustible Trim Clearances Mantel and Mantel Shelf Clearances As with any radiant heat fireplaces all Burntech Fireplaces must comply with building code safety clearances per uni...

Page 16: ...in an accident or malfunction If instructions are not followed the warranty on the product will become null and void 3 1 2 3 4 5 Note that the most important aspect of the installation is the maintena...

Page 17: ...1 One elbow begins the installation procedure and the second elbow is used to finish off each section In all likelihood a 30 degreeoffsetelbowwillprobablybethefirsthardwareusedoff the top of the ancho...

Page 18: ...lination Multiple offsets are permitted if they do not exceed a 45 inclination The total lengths of the two offsets are not required to meet the 75 allowable rule Figure 2 Example 3 Shows a single off...

Page 19: ...re scheduled to install the round top termination unit or any of the flashings or flues that will be exposed to outside weather conditions Venting terminals shall not be recessed into walls or siding...

Page 20: ...ch sensor pointed toward the room out of the fireplace Use six 6 drywalls screws to fasten it in place on the front most part of the firebox ceiling as shown through the six 6 pre drilled holes Attach...

Page 21: ...SOAPY WATER SOLUTION IF A LEAK IS DETECTED TIGHTEN CONNECTIONS AND TEST AGAIN NEVER USE AN OPEN FLAME TO CHECK FOR GAS LEAKS Insert a one way screw into the hole in the front of each bracket and tight...

Page 22: ...d the heat chambers facing the back of the fireplace Figure 35 Place the front log on the grate in front of the top burner pipe with the flat down and the heat chambers toward the burner pipe and the...

Page 23: ...the four 4 screws above and below the control panel face then pull the control panel out far enough to expose the test ports on the valve Figure 41 Unscrew the port marked IN part way and test CAUTION...

Page 24: ...ts a Check with a millivolt meter Should be 250 millivolts or more b Pilot flame making a blowing sound b Pilot needs adjusting see Checking and Adjusting the Pilot on page 22 c Generator wire leads a...

Page 25: ...ncrete slab The concrete strength and durability shall comply with Sections 1903 1904 and 1905 of the International Building Code IBC TABLE R402 2 MINIMUM SPECIFIED COMPRESSIVE STRENGTH OF CONCRETE MI...

Page 26: ...ly b Lines defining areas are approximate only Local conditions may be more or less severe than indicated by region classification A severe classification is where weather conditions result in signifi...

Page 27: ...ded at Burntech Fireplace Solutions s option Nothing in this warranty makes Burntech Fireplace Solutions or any affiliate thereof liable in any respect for any injury or damage to the building or stru...

Reviews: