Commissioning
After receiving and unpacking, check the machine for possible transport dam-
ages. In case of transport damage, please inform your insurance, the transport
company and the manufacturer / supplier.
Transport to the place of installation
Only use suitable lifting and transport equipment such as forklifts or pallet lifts.
Secure the machine against sliding / tilting.
Place of installation
The machine must be standing level and around the machine there has to be suf-
ficient space for operation and maintenance work (approx 1m on all sides). To prevent the penetration
of chemicals into the ground, set up the machine either in a room with solid, waterproof and chemical
resistant floor (no tiles or concrete!) or in a chemical resistant waterproof collection tray which can take
the whole filling volume (safety tray available as an option).
Connections
Connect the overflow of freshwater rinse (PVC pipe D50) with your rinse water treatment. Make a con-
nection to the fresh water inlet (spout D16). Connect inlet and outlet of the cooling (spout D16), de-
pending on the chemical join suction of the lid (D75 / 63) to your exhaust system. Finally connect the
machine to the mains (220V / 50Hz). We presuppose an on site fuse protection of the electric circuit.
Bungard Elektronik GmbH & Co. KG, Rilkestraße 1, 51570 Windeck – Germany