BULLDOG HEAT PUMP Vertical Stacked – Installation Manual
7
© Copyright 2017 CGC Group of Companies, Inc. Installation Manual is Subject to Change without Notice - Last Revised Aug 15, 2017
ELECTRICAL WIRING
Main Wiring
Electrical connections are made to the cabinet. Cabinets have
knockouts for a standard single gang electrical box. Receptacle may
be included with unit. Box must not protrude into cabinet more
than ½” or it will interfere with the chassis installation or removal.
Refer to Guide Specs for further wiring instructions.
DRYWALLING
1.
Attach drywall to front of unit to ensure the
proper fit of acoustic panel as shown in figure
11.
2.
Glue or attach drywall with screws to the front
of cabinet
3.
It is permissible to glue or screw drywall
directly to the side of the cabinet as long as
the riser bundle is not on that side. Please
note that the drywall screw must not be
longer than the drywall thickness plus a
maximum of 3/8”.
4.
Use studs to frame in the riser side of the
cabinet where necessary. Keep screws away
from the riser pipes.
5.
Mount thermostat and connect to thermostat
wire. Ensure that the thermostat is not
mounted in direct sunlight, or within the
supply airstream of the heat pump unit.
6.
Wire thermostat to control board.
7.
Connect power cord at cabinet electrical box.
Figure 8
Figure 10
Front panel clips
Figure 9