Installation
7
Logano plus SB615 - Technical specifications are subject to change without prior notice.
11
7
Installation
7.1
Thermal insulation and outer jacket panels
z
Slide the thermal insulation jacket underneath the boiler
z
Wrap thermal insulation jackets overlapping around the
boiler and fix at the top with 5 spring clips
(Fig. 4, Item 1). Ensure that both door hinge bolts are
installed properly.
z
Open burner door.
z
Place lower thermal insulation pad (Fig. 4, Item 2)
against boiler body front panel and fix to the thermal in-
sulation jacket with 2 spring clips on each side.
z
Place thermal insulation strip (Fig. 4, Item 3) around
the cylindrical section of the boiler body at the top and
fix to the lower insulation pad with 2 spring clips, one
each side.
z
Place top thermal insulation pad against front of boiler
body (Fig. 4, Item 4).
z
Close burner door and secure in position with hex-
bolts.
USER NOTE
Except when fitting the front thermal insula-
tion pad, the combustion chamber must re-
main sealed by the burner door so that the
stainless steel combustion chamber is not
damaged by any welding or grinding work.
Fig. 3
Sliding the thermal insulation jacket underneath the
boiler
Item 1: Hinge bolt
7 747 015 037-04.2RS
1
USER NOTE
When fitting the thermal insulation jacket,
make sure that the woven fabric is on the
outside and the cutouts are at the rear.
WARNING!
RISK OF INJURY
due to burner door falling off when opened.
z
Make sure that both hinge bolts (Fig. 3,
Item 1) are inserted.
Fig. 4
Wrapping thermal insulation jacket around boiler and
fixing
Item 1: Insulating boiler jacket
Item 2: Lower thermal insulation pad
Item 3: Thermal insulation strip
Item 4: Top thermal insulation pad
1
3
2
4
USER NOTE
Take care to correctly position cutouts for
door hinges and threaded hinges of the
burner door.