6
Placing the heating system in operation
Logano G234X – 6 720 811 233 (2017/02)
23
6.8
Commissioning report
▶ Check off preventive maintenance performed.
▶ Record measured values.
Commissioning steps
Page
Comments or measured value
1.
Type of gas
Natural Gas
Propane Gas
2.
Check combustion air supply, air inlet and ventilation openings and flue gas
connection
3.
Check main gas orifice identification (
Tab. 13). Convert to a different gas type,
if necessary.
4.
Fill boiler with water and bleed complete heating system
5.
Measure the gas supply pressure [inches W.C.] or [mbar]
Meas. value: _____________________________
Unit: _____________________________________
6.
Measure the orifice pressure and adjust if necessary [inches W.C.] or [mbar]
Meas. value: _____________________________
Unit: _____________________________________
7.
Leak test during operation
Check ignition flame
Check main burner flame
Check that flue gas system is functioning properly
8.
Check maximum AquaSmart
TM
setting
9.
Install front wall of boiler
10.
Inform operator, hand over technical documentation
11.
Installer:
Signature: _______________________________
12.
Owners/operator:
Signature: _______________________________
Table 12 Commissioning report
Boiler size
Main gas orifice identification (0...8500 ft /0...2591m)
Natural gas
1)
1) Factory setting
LP (propane gas)
2)
2) Convert from natural gas to propane gas only as described in Section 5.4.2, page 13.
38
3.70
2.20
45
3.70
2.40
55
3.50
2.30
64
3.80
2.45
Table 13 Main gas orifice identification
Summary of Contents for G234X/38