2.5 Mounting Procedures
Tools and ancillary equipment
1. Philips head screw driver.
2. QTY 4, ½” x 4” concrete expansion bolts.
3. ½‘” torque wrench.
4. 3/16” allen wrench for electrical connections.
5. Keys (shipped with unit), to be used to open the access panels.
Concrete pad installation requirements.
Use 4 (minimum 4) 1/2” x 4” (PN RHPA-3830) concrete expansion bolts to anchor the steel pedestal
provided with the BTCP EV Charging Station.
WARNING
BTCP EV Charging Station can only be installed onto undamaged concrete slab.
A minimum of 4 expansion bolts should be mounted on the bottom enclosure footer.
In order to install the expansion bolts please follow the following steps:
Installation Steps
1. Drill a hole at the proper drill bit diameter (5/8”). Clean hole thoroughly
PLEASE NOTE: Drill depth required is 3.5 inches.
WARNING
If the drill length is less than specified then bolt will bottom out prior to engaging the bottom
installation footer on the BTCP EV charging station. The system will be able to be rocked or
moved.
2. Insert the expansion bolt sleeve entirely in the hole without the fixture as shown in fig. 2 above.
3. Position the fixture to be anchored, twist the expansion bolt until it is flush with the fixture. Place
enclosure.
4. Tighten the expansion bolt to the specified installation torque.
This document is Property of BTCPower, Inc. and should
not be copied, reproduced, or used as the basis for sale
or manufacture of apparatus without BTCPower's written
permission