51
CHECKLIST — INSTALLATION
LOAD CALCULATION
________________
Heating Load (Btuh)
Condensate Drain
________________
Cooling Load (Btuh)
________________
Unit Level or Pitched Forward
________________
Furnace Model Selection
________________
Internal Tubing Connections
Free of Kinks and Traps
COMBUSTION AND VENT PIPING
________________
External Drain Connection Leak
Tight and Sloped
Termination Location
________________
Condensate Trap Primed before
Start---Up
________________
Vent
Heat Tape Installed if Required
________________
Roof
CHECKLIST --- START---UP
________________
Sidewall
________________
Gas Input Rate (Set Within 2
percent of Rating Plate)
________________
Combustion---Air
________________
Temperature Rise Adjusted
________________
Roof
Thermostat Anticipator
________________
Sidewall
________________
Anticipator Setting Adjusted or
________________
Attic
________________
Cycle Rate (3 Cycles per Hr)
Selected
________________
Crawl Space
Safety Controls Check Operation
________________
Termination Kit---2 Pipe or
Concentric
CHECKLIST --- START---UP
________________
Combustion---Air Pipe Length
________________
Gas Input Rate (Set Within 2
percent of Rating Plate)
________________
Combustion---Air Pipe Elbow
Quantity
________________
Temperature Rise Adjusted
________________
Vent Pipe Length
Thermostat Anticipator
________________
Vent Pipe Elbow Quantity
________________
Anticipator Setting Adjusted or
________________
Pipe Diameter Determined from
Sizing Table
________________
Cycle Rate (3 Cycles per Hr)
Selected
________________
Pipe Sloped To Furnace
Safety Controls Check Operation
Pipe Insulation
________________
Primary Limit
________________
Over Ceilings
________________
Pressure Switches
________________
Low---Ambient Exposed Pipes
355B
A
V