![Brunswick Santini Installation Manual Download Page 5](http://html1.mh-extra.com/html/brunswick/santini/santini_installation-manual_2821250005.webp)
BRUNSWICK INSTALLATION MANUAL
PAGE 5
SANTINI/SUTTON
SLATE ASSEMBLY
(CONTINUED)
FIGURE THREE
Step #8:
With a precision level, level each end slate sec
-
tion by driving wooden slate wedges (provided) between
the top of the baseframe and bottom of the slate as
shown in gure 3. Keep the wedges as close to the
countersink holes as possible.
Step #9:
With both end slates perfectly level, continue
fastening the end slates at the joints. Recheck for level
and if necessary, back the screws out and adjust the
shim position, then retighten the slate attaching screws.
Step #10:
When satised that both end slates are level,
shim, the center slate section as required to obtain a
ush t at both joints, then screw the center slate down.
Step #11:
Slate joints can now be lled with fast setting
rock hard putty. Lightly sand or scrape across joint after
grouting.
FIGURE THREE
FIGURE FOUR
Step #12:
From the end of a bed cloth, cut strips of cloth
approximately 1-1/2” wide by approximately 8” long and
glue the strips to the pocket cutouts. This is important
as this will provide cushioning from ball impact and the
bed cloth will last much longer.
Step #13: Proceed to cloth covering instructions.
FIGURE FOUR