9
Frameworx to LCD Interface Pre-Installation
6.
What type of front desk does the center have?
a.
Command Network
_______
b.
Center Master
_______
c.
Vector Plus
_______
7.
What version of Frameworx scorer software does the customer have? _______
NOTE: Command Network must have Frameworx scorer software version 5.6. Vector Plus
and Centermaster must have Frameworx scorer software version 6.3. If the customer does not
have the proper software, please contact the CRC on behalf of the customer to obtain these
disks. Provide this site survey to the CRC.
IMPORTANT: The customer is responsible to provide a quantity of three IG outlets prer LCD
overhead for the Frameworx LCD Interface. One for each component: Frameworx LCD
Interface, S-video to VGA convertor, and the LCD overhead.
8.
The LCD overheads require different electrical requirements than the old CRT overheads. Please
review the information below with the customer to inform them of their additional electrical responsi-
bilities.
a.
Isolated Ground (IG) outlet is required for the LCD Overhead.
b.
Isolated Ground (IG) outlet is required for the S-video to VGA convertor.
c.
Isolated Ground (IG) outlet is required for the Frameworx LCD Interface.
d.
Three power outlets are required for Frameworx LCD Interface, S-video to VGA convertor,
and the LCD overhead.
e.
LCD WITH INTERFACE ELECTRONICS TOTAL AMPERAGE PERE ONE OVERHEAD (120/230 VOLT)
32" LCD
2.5/1.5
40" LCD
3.5/1.75
46" LCD
4.0/2.0
9.
What is the ceiling height, from the lane surface over the approach area where monitors will be
located? _______
a.
For 32" LCD we recommend 10’-6" (3.2m) ceiling heights, minimum of 9’-6" (2.9m).
b.
For 40" LCD we recommend 10’-10" (3.3m) ceiling heights, minimum of 9’-10" ( 3.0m).
c.
For 46" LCD we recommend 11’-1" (3.4m) ceiling heights, minimum of 10’-1" (3.1m).
NOTE: The LCD monitor may be installed with ceilings lower than the minimum ceiling height
distance, but the customer should be aware the height from the lane to the bottom of the
monitor would be less than 89."
IMPORTANT!: The site survey and overhead certificate must be completed and sent to
Contract Management before the contract can be approved and shipped.