Brocade VDX 6740 Hardware Reference Manual
11
53_1002829_02
Verifying operation
2
NOTE
Power is supplied to the switch as soon as the first power supply is connected and powered on.
3. After POST is complete, verify that the switch power and status LEDs on the port side of the
switch are green.
Verifying operation
After you have powered the system on and POST is complete, verify that the switch is working
properly.
1. Verify that the power supply LEDs are solid green. Refer to
Figure 9
and
Figure 10
for the
location of these LEDs.
2. Verify that the system power LED and the system status LED is solid green. Refer to
Figure 7
and
Figure 7
and for the specific locations of these LEDs.
3. The port LEDs should be lit during POST activities. When POST is complete, only the LEDs for
ports connected to other devices should be green. Refer to
Figure 7
and
Figure 7
for the
specific locations of these LEDs.
Refer to
Table 3
for more details on the LED patterns.