8.2

 

INSPECTION

 

PROCEDURE 

 (1) Daily inspection

 (carried out by operating staff or responsible person) 

Part 

Inspection method 

Limit / criteria for  

putting-out of 

operation 

Remedy 

1. Jack function 

Visually, 
aurally 

The jack goes 
hardly, stammers, 
emits noise etc. 

To clean up and 
grease the jack. If 
the defect will not 
be removed, get the 
jack repaired. 

2. Pawls function 
 
(see Fig. 3) 

Visual inspection 
when jacking up 

Pawls do not snap 
behind dents of the 
ratchet. 

To clean up, 
grease, eventually 
change the spring. 

3. Fixative parts 
 
 

Visual inspection of 
all screws, nuts, 
rivets etc. 

Faulty or missing 
parts; 
 
Released parts 

Replace by new 
ones; 
 
To retighten 
released parts 

 
 
(2) Regular inspection

 (carried out by the competent person) 

Part 

Inspection 

method

 

Limit / criteria for  

putting-out of 

operation

 

Remedy

 

1. Fixative parts 
 
 

Visual inspection 
of all screws, nuts, 
rivets etc. 

Faulty or missing 
parts; 
 
Released parts 

Replace by new 
ones; 
 
To retighten 
released parts 

2. All parts 

Visual inspection 

Outworn or 
damaged parts; 
 
Fouled and 
ungreased parts 
 

Replace by new 
ones; 
 
To take to parts, 
clean up, grease 
and again assemble 

3. Label – marking of 
load capacity on the 
jack 
 
(see Fig. 3) 

Visual inspection 

Load capacity is not 
readable 

To repair or replace 
by new one 

4. Brake 
 
(see Fig. 6 and  
Fig. 7) 

Jack up and lower 
the load with 
weight equal 
approximately to 
the load capacity 
of the jack  

When interrupting 
jacking up the brake 
must hold firmly the 
load in each 
position during 
raising and lowering 

If it will not be so, 
ask for repair and 
adjusting of the 
brake 
 

 

Summary of Contents for 15-00-CM

Page 1: ...INTENANCE FOR RACK JACK WITH A RATCHET CRANK LEVER type 15 00 CM 5t 15 01 CM 10t Peruse the operation manual before using the jack It comprehends substantial security instructions and instructions for...

Page 2: ...APPLICATION OF THE JACK 10 7 2 SAFETY WORK ENVIRONMENT 11 8 CHECK UP ON THE JACK 12 8 1 INSPECTION 12 8 1 1 Inspections types 12 8 1 2 Daily inspection 12 8 1 3 Regular inspection 12 8 1 4 Jack occas...

Page 3: ...egulation ministerial order No 176 2008 of the Collection of Laws as amended as well as requirements of the SN EN ISO 12100 and SN EN 1494 harmonized technical standards 2 3 The jack by its design mee...

Page 4: ...or faultless technique of raising loads Hence verify all national directives regulations and standards whether they contain other information on safety work with your jack 3 2 SECURITY PRINCIPLES WARN...

Page 5: ...ons can be done that will be in accordance with producer s requirements stated in the chapter 11 of this OM IT IS NOT PERMITTED to carry out repairs and maintenance in other manner than specified by t...

Page 6: ...y special storage position 4 3 HANDLING During transportation and handling observe technical regulations and standards in force for work with heavy loads 5 MAIN TECHNICAL SPECIFICATIONS Type Load capa...

Page 7: ...or load approximating to the maximum 0 80 k 1 00 0 12 0 25 Load diagram Load diagram Load diagram Load diagram 1 2 3 4 Percentage of operating time 5 2 MATERIAL AND FINISH 5 2 1 All parts of the jack...

Page 8: ...he jack see chapter 6 5 ALWAYS safeguard the jack against drop at pushing or spreading out of loads i e in horizontal direction A drop can take place when shifting the load and thereby unloading and r...

Page 9: ...through of the brake namely at manipulation with heavier loads In this case release the brake by more point blank motion thereby you will coincidently release the ratchet crank 6 3 RATCHET CRANK LEVER...

Page 10: ...suitable load 10 till 50 of the load capacity At the same time verify whether the jack will hold firmly the load without slipping when lowering and stopping 7 OPERATION 7 1 APPLICATION OF THE JACK 7 1...

Page 11: ...s according to the chapter 3 of this OM 7 2 SAFETY WORK ENVIRONMENT Warning 1 The operating personnel must be demonstrably acquainted with this Operation Manual they must adhere to valid security and...

Page 12: ...inspection also during operation in the interval between regular inspections Qualified employees will determine whether any defect or damage can constitute a hazard and whether the detailed inspectio...

Page 13: ...r inspection carried out by the competent person Part Inspection method Limit criteria for putting out of operation Remedy 1 Fixative parts Visual inspection of all screws nuts rivets etc Faulty or mi...

Page 14: ...ASING 10 1 GENERALLY Before application of the grease remove old grease clean up components with grease solvent and apply new grease Use grease specified by the producer vaseline lubricant grease PM A...

Page 15: ...rying out the maintenance see chapter 6 5 ALWAYS mark disabled or repaired jack with appropriate inscription i e OUT OF OPERATION NEVER carry out maintenance if there is the load on the jack NEVER wor...

Page 16: ...e heat fire as the mean when dismantling parts if the parts are destined for next use 5 Keep the workplace clean and without foreign materials that could get into bearings and other movable parts 6 If...

Page 17: ...Law as amended EP and Council directive 2014 34 EU SN EN ISO 12100 SN EN 1494 SN EN 1127 2 SN EN 1127 1 SN EN 13463 1 Regulation of CBM Czech Bureau of Mine No 22 89 of the Collection of Law SN 33 20...

Page 18: ...destined entirely for underposable raising and lowering of free loads at normal atmospheric conditions in the workplace when observing the specified maximum load capacity Is in conformity with the fol...

Reviews: