Installation 

S19-324D2

Bradley • 

215-1847 Rev. G: ECO 20-05-028 

6/11/2020

IMPORTANT

The installation and location of all safety drench showers, eye and eye/face washes must comply 

with the requirements of ANSI/ISEA Z358.1.

Read this installation manual completely to ensure proper installation, then file it with the owner 

or maintenance department. Compliance and conformity to local codes and ordinances is the 

responsibility  of the installer.

Separate parts from packaging and make sure all parts are accounted for before discarding any 

packaging material. If any parts are missing, do not begin installation until you obtain the missing 

parts.

Installation and maintenance of this system must be completed by a qualified plumber and 

electrician according to the information contained in this installation manual and in compliance 

with all national and local codes. 

 The ANSI/ISEA Z358.1 standard requires an uninterrupted supply of flushing fluid. Bradley 

plumbed emergency fixtures require a minimum of 30 PSI (0.21MPa) flowing pressure. 

Weekly activation must be conducted on all plumbed emergency equipment to ensure a suitable 

flushing fluid supply is present and any sediment build up in the supply line is cleared. Inspect 

safety equipment monthly to address any maintenance issues ensuring the equipment is in good 

operating condition and that there are no signs of wear.

Perform functional test upon relocation of safety equipment.

Workers who may come in contact with potentially hazardous materials should be trained 

regarding the placement and proper operation of emergency equipment per ANSI/ISEA Z358.1.

For questions regarding the operation or installation of this product, visit www.bradleycorp.com or 

call 800-BRADLEY (272.3539). 
Product warranties and parts information may also be found under ”Products” on our web site at 

bradleycorp.com.

Supplies Required

•  Teflon tape or pipe sealant
•  Black, white and green AWG 18 minimum (14 AWG maximum) wire to connect signaling system to electric 

power supply, use copper wire only

•  3/4" hubs and fittings for electrical wiring (all customer supplied hubs and fittings must match the electrical 

rating of the enclosures)

Summary of Contents for S19-324D2D

Page 1: ... Division 2 Groups C and D with Selector Switch Explosion Proof Emergency Signaling System Table of Contents Pre Installation Information 2 3 Components 4 Install Flow Switch and Mount Signaling Assembly 5 Connect Signaling Assembly To Flow Switch 6 Complete Electrical Supply Connections 6 Conduit Seals 6 Test the Signaling System 7 Maintenance 7 Remote Sensing Option 7 Service of Lights 8 Trouble...

Page 2: ...beginning installation and after installation is complete Test the unit for leaks and adequate water flow Main water supply should be ON at all times unless system is being serviced Provisions shall be made to prevent unauthorized shutoff CAUTION Supply the unit with clean potable water NOTICE Before installing this product ensure that there are adequate clearances around the product and activatio...

Page 3: ...s require a minimum of 30 PSI 0 21MPa flowing pressure Weekly activation must be conducted on all plumbed emergency equipment to ensure a suitable flushing fluid supply is present and any sediment build up in the supply line is cleared Inspect safety equipment monthly to address any maintenance issues ensuring the equipment is in good operating condition and that there are no signs of wear Perform...

Page 4: ...ub Plugged Brass Sensor Body Brass Adapter and Tee 2 7 8 73mm 1 5 8 41mm NEMA 4X Junction Box and Cover Electrical Quick Disconnect Male 3 13 16 97mm 5 5 16 135mm Red Blue Black Remote Sensing 13 1 8 334mm System is prewired Installer connects ONLY ground black and white wires 1 2 eyewash or 1 drench shower NPT Inlet and Outlet 2 3 8 60mm for eyewash or 3 9 16 91mm for drench shower ...

Page 5: ...em may be mounted directly to the drench shower piping using the supplied U bolts and nuts The signaling system can also be bolted to a flat surface such as a wall hardware for this type of installation is NOT supplied NOTICE If the water supply line will be exposed to temperatures at or below freezing the inlet supply must be freeze protected 6 inches above the flow switch tee freeze protection b...

Page 6: ... counter clock wise B With the remaining conduit cable run provided electric power conduit and hubs into an unused 3 4 conduit port of the control box Connect the provided wires in the conduit to the floating terminal block per the wiring schematic Compliance and conformity to local codes and ordinances is the responsibility of the installer D Once the connections are made close the access cover b...

Page 7: ...will automatically reset the silence feature The signaling system is designed to work properly even if both the eyewash and drench shower are used simultaneously The signaling system will continue to operate so long as either the eyewash or drench shower is still in use Signaling System Maintenance The Bradley Emergency Signaling System is designed to be virtually maintenance free An occasional da...

Page 8: ...from the terminal location C Remove the nut on the stem of the light which attaches it to the enclosure Remove the entire light D Remove the gasket if present to expose the four screws which retain the dome E Remove the screws take off the dome and the LED array is now visible Press and turn the LED array to remove Replace as needed with the same size LED array and color F Reverse the disassemble ...

Page 9: ...mponent failure Check light connections and filament in the light Area light does not operate No power to the signal station Check that the circuit breaker or fuse is supplying power to the signal station Component failure Check the two 3 Amp 24VDC fuses on the print circuit board in the signal station enclosure No input power Check that there is 24VDC being supplied from the power supply mounted ...

Page 10: ... 11 2020 Bradley 215 1847 Rev G ECO 20 05 028 30 35 84 31 32 33 34 36 34 38 76 84 36 61 34 36 33 34 20 38 77 84 61 62 63 43 41 32 33 34 36 39 34 33 34 37 35 84 3 33 35 84 2 1 64 65 60 38 84 36 81 80 62 36 S19 324D2 Service Parts ...

Page 11: ...55 070 1 Enclosure Class 1 Div 1 2 60 S70 176 1 Exp Alarm Enclosure MN heat traced units only 60 140 1157 1 Bracket Alarm Box Exp Pipe Mount non heat traced units Item Part No Qty Description 61 160 514 5 Screw 3 8 16x1 0 BTN 62 161 157 5 Nut 3 8 16x1 0 BTN 63 140 1158 1 Bracket Alarm J Box EXP 64 269 594 2 U Bolt SST 65 161 065 4 Nut 3 8 16 Hex 76 269 1588 1 Conduit Flexible 3 ft 77 S90 643 1 Con...

Reviews: