Boss Solar Strip Thermal Solar Pool Heating | INSTALLATION MANUAL
5
Revision:
C
Revision Date:
18/11/2021
MANIFOLD INSTALLATION
STEP 1:
Taking note of which pipe is flow and return,
complete the PVC pipework from the gutter up, utilising
40mm PVC pressure pipe.
The FLOW pipe (Water to Roof) will require a 45° elbow and
Vacrel installed at the very top of the system.
The RETURN pipe (Water to Pool) requires two 90° elbows
and one end cap at the very bottom of the system.
METAL ROOF
Each EzyClip is supplied with two screws, which are installed
at opposite corners of the clip.
Mark the corners where you wish to install the screws and
apply a bead of silicone to the roof. Place the EzyClip on top
and fix using the two supplied screws. Snap the PVC
manifold system into place.
TILE ROOF
Lift the tile and slide the EzyTie underneath until it hooks
onto the below tile. For extra security you may wish to apply
a bead of silicone before releasing the tile. Lay the PVC Pipe
over the top. If there is excess rubber, fold the EzyTie back
on itself and rest the PVC manifold on top. Slide the supplied
UV Resistant cable tie into the appropriate hole. Loop the
cable tie around the pipe and tighten until firm. Do not over
tighten. Trim excess cable tie with side cutters or scissors.
Ensure the pipework is securely fixed to the roof using the mounting system that matches your roof type
Summary of Contents for PROSOLAR
Page 1: ......