Job steps
A job always begins with the start step and ends with the end step; the two steps are preset in a new job.
Different or identical job steps can be inserted between these two steps. Selection, number, and order
of these job steps depend on the required tightening process. New steps are always inserted in the job
before a selected step. A job can contain no more than 20 job steps.
The following table provides an overview of the job steps available.
9.6.3
Create new job/change job
New jobs can be configured or existing jobs can be edited.
Accept values
Click
OK
to apply the edited values to the tightening program. Click
Cancel
to discard your changes.
The dialog window will be closed in either case.
Click
Save
to apply the tightening program.
9.6.3.1
Start step
Every job has exactly one start step. The properties of the start step apply to the complete job sequence.
General
Table 9–22:
Available job steps
Element
Designation
Explanation
See page
Start step
Starts the job
ID input
Step for the treatment of an ID input
Single program
Step for basic processing
End step
Completes the job
As of Nexo firmware version 1200, the sub-menus in the steps are no longer opened by
drop down menu and instead by clicking on the plus sign (left).
Double clicking the step or the respective icon will open a dialog where the associated
parameters can be entered.
Table 9–23:
Start step dialog – General panel
Element
Description
Name
Step name
Admissible characters are ASCII characters, numbers, spaces, hyphens,
dashes and underscore.
Comments
Enter a comment for the step.
Admissible characters are ASCII characters, numbers, spaces, hyphens,
dashes and underscore.