Figure 8

11.  Pass a cable tie through the copper U-ends as close to the metal bracket 

as possible, and gently tighten to bring the four rows of the evaporator 
together securely (Fig.9).

Figure 9

12.  Install the new evaporator coil into the unit, and secure the 5 screws in the 

order shown in Fig.10. Remove the temporary support rod.

Figure 10

13.  Using the correct procedure with nitrogen, braze the coil’s inlet and outlet 

connections (Fig.11).

Figure 11

14.  Evacuate and recharge the unit (refer to the installation manual for correct 

specifi cations and procedure), reinstall all panels and screws, turn 
the power back on to the unit and conduct a test run to ensure correct 
operation.

Figure 12