Installation
Tap Installation
1
Identify a suitable location for the undercounter unit. It should
be positioned within 1.0m of the faucet, and within 2.0m of
suitable services connections. Allow enough space to fit the
ventilation ducting system.
Service Requirements
Water: Mains potable water – internally regulated to 1.3bar. Min
mains pressure 1.3bar.
Electricity: 13A supply – Earth Leakage Protected.
2
33 - 35mm
3
187mm
4
When planning and providing
for the connection to the
services, always allow for
easily accessible service isolator
fittings and for the position of an
external water filter.
Identify a suitable position for the
swan neck faucet. A 33-35mm
(max) hole is required.
When positioning to drain over
an existing sink bowl, allow for
the reach of the swan neck or
otherwise the position of any
optional drip tray.