REV. 02 - MARCH 2021 - BLÜCHER
®
CONNECTED ROOF
11
The Monitor should ideally be installed at the same invert level as the roof drain, giving the
system the best conditions to measure the right water level. If this is not possible, and the
Monitor ends up higher/lower than the roof drain, you will need to offset the water levels on
the Monitor in the config file (see chapter 7.5).
Before installing the Monitor ensure that the surrounding
roof area and the bracket are cleaned carefully before
application of the recommended glue/sealer for the roof
type.
1. Clean Bracket
2. Clean Roof
3. Glue
Use glue/sealer
recommended for
you roof type
40 mm - 60 mm
Position the Monitor, including bracket, 40-60
mm from the edge of the drain. If the drain has
a leaf guard, the 40-60 mm distance is from
the edge of the leaf guard to the bracket.