STORAGE AND TRANSPORTATION REGULATIONS

•  Store the unit in the manufacturer’s original packaging box in a dry closed ventilated premise with temperature range 

up +5 ˚С  to +40 ˚С  and relative humidity up to 70 %.

•  Storage environment must not contain aggressive vapours and chemical mixtures provoking corrosion, insulation, and sealing 

deformation.

•  Use suitable hoist machinery for handling and storage operations to prevent possible damage to the unit.
•  Follow the handling requirements applicable for the particular type of cargo.
•  The unit can be carried in the original packaging by any mode of transport provided proper protection against precipitation and 

mechanical damage. The unit must be transported only in the working position.

•  Avoid sharp blows, scratches, or rough handling during loading and unloading.
•  Prior to the initial power-up after transportation at low temperatures allow the unit to warm up at room temperature for at least 3-4 

hours.

DISCONNECT THE UNIT FROM POWER SUPPLY BEFORE 

ANY MAINTENANCE OPERATIONS!

TECHNICAL MAINTENANCE

TROUBLESHOOTING

The technical maintenance includes periodic cleaning of the surfaces from accumulated dust and dirt. The impeller blades require 
thorough cleaning once in 6 months. Clean the blades with a soft brush or a vacuum cleaner. While cleaning the fan be careful not to 
displace the impeller counter weights. Protect the electric motor against ingress of liquid.

PROBLEM

POSSIBLE REASONS

TROUBLESHOOTING

The fan does not start.

No power supply.

Make sure that the unit is properly connected to the power 
mains and make any corrections, if necessary.

Low air flow.

The ventilation system is soiled 
or damaged.

Make sure the air ducts are clean and intact. Clean them if 
necessary.

Noise, vibration.

The fan impeller is soiled.

Clean the impellers.

The screw connection is loose.

Tighten the fastening screws.

Summary of Contents for ISO-RB EC 100

Page 1: ...Centrifugal duct fan USER S MANUAL EN ISO RB EC...

Page 2: ...to the receiving operator CONTENTS UNIT INSTALLATION AND OPERATION SAFETY PRECAUTIONS Disconnect the unit from power mains prior to any installation operations Unpack the unit with care The unit must...

Page 3: ...t the electric parts of the unit against ingress of water Do not allow children to operate the unit Disconnect the unit from power mains prior to any technical maintenance Do not store any explosive o...

Page 4: ...s substances toxic substances dust pathogenic germs THE UNIT SHOULD NOT BE OPERATED BY CHILDREN OR PERSONS WITH REDUCED PHYSICAL MENTAL OR SENSORY CAPACITIES OR THOSE WITHOUT THE APPROPRIATE TRAINING...

Page 5: ...B B1 A1 A2 A3 A ISO RB EC 100 ISO RB EC 125 ISO RB EC 150 ISO RB EC 160 ISO RB EC 200 ISO RB EC 250 ISO RB EC 315 ISO RB EC 355 ISO RB EC 400 ISO RB EC 450 ISO RB EC 500 Unit voltage V 50 60 Hz 1 230...

Page 6: ...arrow on the fan casing UNIT DESIGN AND OPERATING PRINCIPLE INSTALLATION AND CONNECTION WHILE INSTALLING THE UNIT ENSURE CONVENIENT ACCESS FOR SUBSEQUENT MAINTENANCE AND REPAIR THE UNIT MUST BE MOUNT...

Page 7: ...ing to the markings 3 Fix the fan on the mounting brackets using the appropriate fasteners 4 Connecttheairducts purchasedseparately tothefanspigots 5 Unscrew the terminal box cover 6 Make the electric...

Page 8: ...section selection must be based on the maximum load current maximum conductor temperature depending on the wire type insulation length and installation method The external power input must be equippe...

Page 9: ...Prior to the initial power up after transportation at low temperatures allow the unit to warm up at room temperature for at least 3 4 hours DISCONNECT THE UNIT FROM POWER SUPPLY BEFORE ANY MAINTENANC...

Page 10: ...y does not apply to the following cases User s failure to submit the unit with the entire delivery package as stated in the user s manual including submission with missing component parts previously d...

Page 11: ...e user s manual The warranty terms are acknowledged and accepted Customer s Signature The ISO RB EC _______________________________ unit has been connected to power mains pursuant to the requirements...

Page 12: ...www blaubergventilatoren de B143 2EN 01...

Reviews: