BLACKMER LGB1E Installation, Operation And Maintenance Instructions Download Page 3

501-A00    Page 3/12 

INSTALLATION 

NOTICE: 

Blackmer pumps must only be installed in systems 
designed by qualified engineering personnel.  System 
design must conform with all applicable regulations and 
codes and provide warning of all system hazards. 

 

NOTICE: 

This pump shall be installed in accordance with the 
requirements of NFPA 58 all applicable local, state and 
national regulations. 

 

 

  Install, ground and wire to local and 

National Electrical Code requirements. 

  Install an all-leg disconnect switch near 

the unit motor. 

  Disconnect and lockout electrical power 

before installation or service 

 

Electrical supply MUST match motor 
nameplate specifications. 

Hazardous voltage. 

Can shock, burn or 

cause death. 

  Motors equipped with thermal protection automatically 

disconnect motor electrical circuit when overload exists.  
Motor can start unexpectedly and without warning. 

 
PRE-INSTALLATION CLEANING 

NOTICE: 

New pumps contain residual test fluid and rust inhibitor.  
If necessary, flush pump prior to use. 

Foreign matter entering the pump WILL cause extensive 
damage.  The supply tank and intake piping MUST be 
cleaned and flushed prior to pump installation and operation. 
 

LOCATION AND PIPING 

Pump life and performance will be significantly reduced when 
installed in an improperly designed system. Before starting 
the layout and installation of the piping system, review the 
following suggestions: 

1.  Locate the pump as near as possible to the source of 

supply to avoid excessive inlet pipe friction. 

2.  The inlet line should be at least as large as the intake 

port on the pump. It should slope downward to the pump, 
and should not contain any upward loops. Eliminate 
restrictions such as sharp bends; globe valves, 
unnecessary elbows, and undersized strainers. 

3.  A strainer must be installed in the inlet line to protect the 

pump from foreign matter. The strainer should be located 
at least 24" (0.6m) from the pump, and have a net open 
area of at least four times the area of the intake piping. 
Strainers must be cleaned regularly to avoid pump 
starvation. 

4.  The intake and discharge piping system must be free of 

all leaks. 

5.  Expansion joints, placed at least 36" (0.9m) from the 

pump, will compensate for expansion and contraction of 
the pipes. Contact the flexible connector/hose 
manufacturer for required maintenance/care and design 
assistance in their use. 

6.  ALL piping and fittings MUST be properly supported to 

prevent any piping loads from being placed on the pump. 

7.  Install pressure gauges in the NPT ports provided in the 

pump casing to check pump performance at start up. 

8.  Check alignment of pipes to pump to avoid strains, which 

might later cause misalignment.  See Figure 2.  Unbolt 
flanges or break union joints.  Pipes should not spring 
away or drop down.  After pump has been in operation 
for a week or two, completely recheck alignment. 

 

Figure 2 

9.  The external bypass line should be 1/2" (12.7 mm) 

diameter pipe and can be piped back to either the liquid 
or vapor section of the tank. See Figure 3 

10.  The use of a vapor return line will speed up delivery by 

preventing pressure build up at the receiving tank and 
pressure reduction in the supply tank. 

11.  Keeping the liquefied gas systems full of liquid, even 

when idle, will keep the O-rings from changing shape, 
shrinking or super cooling. Evaporation of liquefied gas 
leaves an abrasive powder on the surface which can 
cause wear to the pump, meter, and seals. 

 
 

COMBINATION PUMP RELIEF VALVE AND 
BACK-TO-TANK BYPASS VALVE 

The built-in spring loaded pump relief valve on the LG1 pump 
models has a dual purpose.  The valve provides an external 
bypass back to the tank to provide relief of excess pressure.  
The valve also will act as an internal relief valve recirculating 
fluid within the pump to provide relief of excess pressure if the 
separate back-to-tank line is closed. See Figure 3. Refer to 
“Relief Valve Setting and Adjustment” for proper valve setting 
and adjustment procedure. 
 

 

 

Figure 3 

Bypass Valve 

Mounting

 

Summary of Contents for LGB1E

Page 1: ... product or in the manual look for one of the following signal words and be alert to the potential for personal injury death or major property damage Warns of hazards that WILL cause serious personal injury death or major property damage Warns of hazards that CAN cause serious personal injury death or major property damage Warns of hazards that CAN cause personal injury or property damage NOTICE I...

Page 2: ...jor property damage or death Hazardous or toxic fluids can cause serious injury Do not operate without guard in place PUMP DATA PUMP IDENTIFICATION A pump Identification tag containing the pump serial number I D number and model designation is attached to each pump It is recommended that the data from this tag be recorded and filed for future reference If replacement parts are needed or if informa...

Page 3: ... 0 6m from the pump and have a net open area of at least four times the area of the intake piping Strainers must be cleaned regularly to avoid pump starvation 4 The intake and discharge piping system must be free of all leaks 5 Expansion joints placed at least 36 0 9m from the pump will compensate for expansion and contraction of the pipes Contact the flexible connector hose manufacturer for requi...

Page 4: ...a footed motor is used the motor must not be secured to baseplate COUPLING ALIGNMENT The pump must be directly coupled to a gear reducer and or driver with a flexible coupling Verify coupling alignment after installation of new or rebuilt pumps Both angular and parallel coupling alignment MUST be maintained between the pump gear motor etc in accordance with manufacturer s instructions See Figure 5...

Page 5: ...ions 4 Check for leakage from the piping and equipment 5 Check for excessive noise vibration or overheating of the pump reducer and motor 6 If possible check the flow rate 7 With the manual valve in the bypass line OPEN check the pressure setting of the relief valve by slowly closing a valve in the discharge line and reading the pressure gauge As the valve in the discharge line is closed the pump ...

Page 6: ... appropriate procedures and warnings as presented in this manual Hazardous or toxic fluids can cause serious injury SCHEDULED MAINTENANCE STRAINERS Strainers must be cleaned regularly to avoid pump starvation Schedule will depend upon the application and conditions LUBRICATION NOTICE To avoid possible entanglement in moving parts do not lubricate pump bearings or any other parts while pump is runn...

Page 7: ...from the shaft end protruding through the head 20 a Bend up the engaged lockwasher tang and rotate the locknut counterclockwise to remove it from the shaft b Slide the lockwasher off the shaft Inspect the lockwasher for damage and replace as required 6 Clean the shaft portion protruding through the head thoroughly making sure the shaft is free of nicks and burrs This will prevent damage to the mec...

Page 8: ... the head A Left Hand rotation pump will have the drive end of the shaft long end protruding through the head 20 with the bearing cover on the cylinder 13 Apply a light coating of quality O ring lubricant to the shaft end to be inserted into the cylinder 14 Insert the shaft into the cylinder 12 Carefully slide the shaft through the installed mechanical seal 153 and bearing Align the notch in the r...

Page 9: ...followed by a locknut 24A with the tapered end inward Ensure the inner tang A of the lockwasher is located in the slot in the shaft threads bending it slightly if necessary 39 Tighten both locknuts 24B to ensure that the bearings 24 are bottomed in the head recess DO NOT overtighten and bend or shear the lockwasher inner tang 40 Loosen both locknuts 24A one complete turn 41 Tighten one locknut 24A...

Page 10: ... the relief valve adjusting screw 2 with locknut 3 into the valve cover 4 until it makes contact with the spring guide 7 9 After the relief valve has been adjusted tighten the Locknut 3 NOTICE The relief valve setting MUST be tested and adjusted more precisely before putting the pump into service Refer to Relief Valve Setting and Adjustment 10 Refer to Pre Start Up Check List and Start Up Procedur...

Page 11: ...tended periods with a closed discharge line 3 Pump not securely mounted 4 Misalignment of pump or motor base mounted pumps 5 Bearings worn or damaged 6 Vibration from improperly anchored piping 7 Bent shaft or drive coupling misaligned 8 Excessively worn rotor 9 Malfunctioning valve in the system 10 Relief valve setting too low 11 Damaged vanes see following category Damaged Vanes 1 Foreign object...

Page 12: ... 215 GPM HXL 6 8 10 Sliding Vane Pumps 130 to 2 220 GPM Refineries Terminals Barges Ships Reciprocating Gas Compressors Liquefied Gas Transfer Boosting Vapor Recovery Hand Operated Pumps Dispensing Transfer In line Accessories Gear Reducers Bypass Valves Strainers Visit www blackmer com for complete information on all Blackmer products 1809 Century Avenue Grand Rapids Michigan 49503 1530 U S A Tel...

Reviews: